Hello - first time poster. Before you get angry, I have read through the forums and not been able to find a solution that works.
Here's what I'm trying to do.
For a number of projects with defined start dates over the next 30 years, I want to create a data modeller that allows me to flex project duration to recalculate finish date and total duration over the life of the facility (total project days). There are number of various scenarios in durations that can be considered, and i'd like to use this data modeller to reshoot a gantt chart.
I started by building a parameter with a defined range (days). This parameter, and the associated measure, was meant to be used for the Duration Value to determine a new finish date for each scheduled project.
my formula...
Hi @derekalstein ,
Sorry for that the information you have provided is not making the problem clear to me. Can you please share more details to help us clarify your scenario?
Please provide me with more details about your table and your problem or share me with your pbix file after removing sensitive data.
Refer to:
How to provide sample data in the Power BI Forum
How to Get Your Question Answered Quickly
Best Regards,
Jianbo Li
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
I hope this helps...
The problem seems to lie in the varFinish code. The interval value (in days) is being set by Outage[Duration Value], which is linked to a parameter between 10-40. When I use this reference to the dynamic value, the new date (varFinish) does not move from the start date - ie the number seems to be recognized as 0. But if i manually change the internval reference from Outage[Duration Value] to just a random number, the formula properly moves the date by that number of defined days.
Join us in Barcelona for FabCon and SQLCon, the Fabric, Power BI, SQL, and AI community event. Save €200 with code FABCMTY200.
Join Data Days 2026: 60 days of free live/on-demand sessions, challenges, study groups, and certification opportunities.
| User | Count |
|---|---|
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
| User | Count |
|---|---|
| 5 | |
| 3 | |
| 3 | |
| 2 | |
| 2 |