I have a set of of data that has a list of projects and the dates at which they hit set milestones - I want to be able to understand which milestone is next for each project. I have generated a sample data set below to illustrate.
I believe the code should be close to below, however to add corresponding stage column I am required to do a lookup from a result generated in the summary, which DAX doesn't allow.
Summary= ADDCOLUMNS(
SUMMARIZE(Table,'Table'[Project]),
"Next Milestone Date", CALCULATE(MIN('Table'[Event Date], 'Table'[Status]="U")))
Status: C = Complete, U = Uncomplete
| Project | Stage | Event Date | Status |
| Project A | 1 | 01/09/2018 | C |
| Project A | 2 | 01/11/2018 | C |
| Project A | 3 | 01/05/2019 | U |
| Project A | 4 | 01/08/2019 | U |
| Project A | 5 | 01/01/2020 | U |
| Project A | 6 | 01/05/2020 | U |
| Project B | 1 | 01/01/2019 | C |
| Project B | 2 | 01/02/2019 | U |
| Project B | 3 | 01/08/2019 | U |
| Project B | 4 | 01/01/2020 | U |
| Project B | 5 | 01/02/2020 | U |
| Project B | 6 | 01/07/2020 | U |
| Project C | 1 | 01/10/2018 | C |
| Project C | 2 | 01/12/2018 | C |
| Project C | 3 | 01/01/2019 | C |
| Project C | 4 | 01/02/2019 | U |
| Project C | 5 | 01/05/2019 | U |
| Project C | 6 | 01/07/2019 | U |
| Project | Next Event | Next Stage |
| Project A | 01/05/2019 | 3 |
| Project B | 01/02/2019 | 2 |
| Project C | 01/02/2019 | 4 |
Solved! Go to Solution.
Hi @Anonymous
Try this:
Summary =
ADDCOLUMNS (
ADDCOLUMNS (
SUMMARIZE ( 'Table'; 'Table'[Project] );
"Next Milestone Date"; CALCULATE ( MIN ( 'Table'[Event Date] ); 'Table'[Status] = "U" )
);
"Next Stage"; LOOKUPVALUE (
'Table'[Stage];
'Table'[Event Date]; [Next Milestone Date];
'Table'[Project]; [Project]
)
)
@AlB Thanks for the response.
Although I agree/understand the logic. Your solution generates the error, "a table of multiple values was supplier where a single value was expected'
Vote for your favorite vizzies from the Power BI World Championship submissions!
If you love stickers, then you will definitely want to check out our Community Sticker Challenge!
Check out the January 2026 Power BI update to learn about new features.
| User | Count |
|---|---|
| 62 | |
| 53 | |
| 42 | |
| 20 | |
| 17 |
| User | Count |
|---|---|
| 122 | |
| 104 | |
| 45 | |
| 31 | |
| 24 |