Trying to calculate Days between 2 date columns. Both Columns have nulls or no values

There is Actual Start and Actual End Date. Both columns have null values as project is in progress or no given date. Keep getting errors on below. Any suggestions? Just trying to get a number value on the difference between these 2 columns. Thanks

 

Days Between = If('BI Projects'[Actual Start]=BLANK(),"",DATEDIFF('BI Projects'[Actual Start], 'BI Projects'[Actual End],DAY))

1 ACCEPTED SOLUTION
tamerj1
Super User
Super User

Hi @ResearchDev 
PLease try

Days Between =
IF (
    'BI Projects'[Actual Start] <> BLANK ()
        && 'BI Projects'[Actual End] <> BLANK (),
    DATEDIFF ( 'BI Projects'[Actual Start], 'BI Projects'[Actual End], DAY )
)

View solution in original post

3 REPLIES 3
ResearchDev
Helper II
Helper II

Thanks so much! Worked like magic!

tamerj1
Super User
Super User

Hi @ResearchDev 
PLease try

Days Between =
IF (
    'BI Projects'[Actual Start] <> BLANK ()
        && 'BI Projects'[Actual End] <> BLANK (),
    DATEDIFF ( 'BI Projects'[Actual Start], 'BI Projects'[Actual End], DAY )
)

Thanks so much!

Helpful resources

Announcements
PBI Sept Update Carousel

Power BI September 2023 Update

Take a look at the September 2023 Power BI update to learn more.

Learn Live

Learn Live: Event Series

Join Microsoft Reactor and learn from developers.

Dashboard in a day with date

Exclusive opportunity for Women!

Join us for a free, hands-on Microsoft workshop led by women trainers for women where you will learn how to build a Dashboard in a Day!

Top Solution Authors