Hi,
I am hoping some can help me.
I have two data tables. A lookup table called Areas. In this there are two fields, Area and Building.
I have another table called Daily Task. In this table is a field called Building (that I use to establish a relationship with the lookup table) and additional fields called Total Tasks and Total Task Completed.
I want to be able to calculate the percentages of all tasks completed. I have the following formula:
Daily Tasks Completed = CALCULATE(SUM('Daily Tasks'[Total Completed Tasks]) / CALCULATE(SUM('Daily Tasks'[Total Tasks])))
The problem I have is that at any point in the day a record could be created for a building and then throughout the day the task completion numbers will change.
At the moment only two records have been created but I know there are ten buildings in total and that a record will be created for them by the end of the day.
My calculation works fine at an individual row level. However, my Total % is not representative of all 10 buildings.
For Example:
Building Total Tasks Total Task Completed %
Building 1 21 5 23.81
Building 2 21 3 14.29
Total % 19.05 (This is visualised as a score card)
How do I make my Total % calculation as a representation of all 10 buildings and not just the ones that I have currently got records for?
Thanks,
Boycie92
Solved! Go to Solution.
@Boycie92 , Not very clear. If is just a display, make sure you have building dimension and use show item with no data.
If you want to divide my number of buildings. Again you need a separate building dimension
Distinctcount(Building[Building])
@Boycie92
What would be the total task for buildings that are not in the Daily Task table? is it 21 for all? If so, try the following:
Daily Tasks Completed =
Divide(
CALCULATE(
SUM('Daily Tasks'[Total Completed Tasks]),
(COUNTROWS(values(AREAS[Builsing])) * 21
)
⭕ Subscribe and learn Power BI from these videos
⚪ Website ⚪ LinkedIn ⚪ PBI User Group
@Boycie92 , I think your formula should work for 10 buildings. can share the problem answer and what you need
Daily Tasks Completed =
Divide( CALCULATE(SUM('Daily Tasks'[Total Completed Tasks]) , CALCULATE(SUM('Daily Tasks'[Total Tasks]))))
Hi @amitchandak
The formula will work for the 10 buildings once all of the records have been created. However, what I need is to be able to trick Power BI into thinking all buildings have a record just now, even though there are only two.
This way my total % will be based on the 10 buildings and not the 2 records I currently have. Is that possible?
Thanks,
Boycie92
@Boycie92
What would be the total task for buildings that are not in the Daily Task table? is it 21 for all? If so, try the following:
Daily Tasks Completed =
Divide(
CALCULATE(
SUM('Daily Tasks'[Total Completed Tasks]),
(COUNTROWS(values(AREAS[Builsing])) * 21
)
⭕ Subscribe and learn Power BI from these videos
⚪ Website ⚪ LinkedIn ⚪ PBI User Group
@Boycie92 , Not very clear. If is just a display, make sure you have building dimension and use show item with no data.
If you want to divide my number of buildings. Again you need a separate building dimension
Distinctcount(Building[Building])
Vote for your favorite vizzies from the Power BI World Championship submissions!
If you love stickers, then you will definitely want to check out our Community Sticker Challenge!
Check out the January 2026 Power BI update to learn about new features.
| User | Count |
|---|---|
| 64 | |
| 50 | |
| 42 | |
| 23 | |
| 20 |
| User | Count |
|---|---|
| 139 | |
| 116 | |
| 54 | |
| 37 | |
| 31 |