Time format greater than 24 hours

Hi all I am working on a Power BI report  in which I am dealing with time values. My issue is that when I sum up a column and then try to display the total in PBI it truncates the time value to 24 hours or less. The value I am summing is in a decimal format.  For example I have a total of 21.20327546 which should then be displayed as 508:52:43. But in PBI it only shows 08:52:43.

 

I have tried to use FORMAT([measure], "dd:hh:nn:ss") but this format looses one day in the calculation. 508 hours is 21.166667 days.  But when I display in a card the value I see is 20:04:52:43.  The minutes and seconds are correct but the rest is wrong.

 

My raw data is :

flow_time

0.0192824074
0.0867708333
0.0994097222
0.1202662037
0.1174421296
0.0367592593
0.0013541667
0.0219444444
0.0866898148
0.2036111111
0.2071296296
0.0450231481
0.0433796296
0.0568287037
0.0667013889
0.1135416667
0.1173726852
19.7597685185

 

Can any one let me know how to get this to display as 508:52:43 in PBI?

1 ACCEPTED SOLUTION
PC2790
Community Champion
Community Champion

Hey @weeksd ,

 

Can you once try this:

 

Required = 
var _sum = sum(TimeTable[flow_time])
VAR hours =  INT( _sum * 24 )
VAR Minutes = MINUTE(_sum)
VAR Seconds = SECOND(_sum)
RETURN
Hours & ":" & Minutes & ":" & Seconds

PC2790_0-1658897793934.png

 

 

View solution in original post

4 REPLIES 4
PC2790
Community Champion
Community Champion

Hey @weeksd ,

 

Can you once try this:

 

Required = 
var _sum = sum(TimeTable[flow_time])
VAR hours =  INT( _sum * 24 )
VAR Minutes = MINUTE(_sum)
VAR Seconds = SECOND(_sum)
RETURN
Hours & ":" & Minutes & ":" & Seconds

PC2790_0-1658897793934.png

 

 

Hello, I was having the same problem and your solution partially solved it. 

I have a column with some negative duration value (due to a difference between worked time and planned working time) and when these negative value convert to hh:mm:ss the have 1 hour added to the result

Ex : instead of obtaining "-0:55:0" I obtain "-1:55:0"

 

Is there something to do ?

I tried to an if statement to add one hour to the hour Var if a value is negative but I don't really understand how to write with the variable

I just ran across this same issue and was able to use your solution! Thank you!

amitchandak
Super User
Super User

@weeksd , refer two display code in this blog

https://radacad.com/calculate-duration-in-days-hours-minutes-and-seconds-dynamically-in-power-bi-usi...

Share with Power BI Enthusiasts: Full Power BI Video (20 Hours) YouTube
Microsoft Fabric Series 60+ Videos YouTube
Microsoft Fabric Hindi End to End YouTube

Helpful resources

Announcements
November Power BI Update Carousel

Power BI Monthly Update - November 2025

Check out the November 2025 Power BI update to learn about new features.

Fabric Data Days Carousel

Fabric Data Days

Advance your Data & AI career with 50 days of live learning, contests, hands-on challenges, study groups & certifications and more!

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.

Top Solution Authors
Top Kudoed Authors