Hi,
Need help.!
I want to summarize without coloums have no date.
anyone know how to do?
cheers,
Agnes
Solved! Go to Solution.
Hi @Anonymous,
Based on my test, you could refer below formula:
Finish Actual_Over = SUMMARIZE(CALCULATETABLE('Dp List','DP List'[Finish Actual]<>BLANK()), 'DP List' [finish Actual], "DP List Finish Actual#", COUNT('DP List'[D/P&BOM]))
Result:
Hope it could help you.
Regards,
Daniel He
Hi @Anonymous,
What is your desired result, could you please post your desired result if possible?
Regards,
Daniel He
Hi,
I want to take and count with only date.!
Hi @Anonymous,
You could try to ues below formula to filter the data without blank:
Finish Actual_Over = SUMMARIZE('Dp List', 'DP List' [finish Actual], "DP List Finish Actual#", CALCULATE(COUNT('DP List'[D/P&BOM]), FILTER('DP List', 'DP List' [finish Actual]<>BLANK())))
If it still could work for you, could you please share your pbix file to hava a test if possible?
Regards,
Daniel He
Hi
First of all thanks for your reply.
I just did try the fomula and it didn't count blank but take the blank in the table.
is there a way not to take the blank in first place?
here is the the file.!
thanks,
Hi @Anonymous,
Based on my test, you could refer below formula:
Finish Actual_Over = SUMMARIZE(CALCULATETABLE('Dp List','DP List'[Finish Actual]<>BLANK()), 'DP List' [finish Actual], "DP List Finish Actual#", COUNT('DP List'[D/P&BOM]))
Result:
Hope it could help you.
Regards,
Daniel He
Thank you so much.! this is exactly what i wanted.
Can i please ask you one more question.?
Please find the attached file.
I want to analyse the plan vs actual progress by choosing many options which are in slicers.
For example, choosing discipline piping > deck MDK > module P03 like that..
Whenever i choose the slicer, the graph get incorrect.?
I am pretty sure that it is possible, i have no clue.
Basically i want to see the plan lines 0%-100% which slicers i choose with progressed line if there is progress.
Thanks,!
Hi @Anonymous,
It's pleasant that your problem could be solved and I suggest you recreate a topic for your new problem.
Regards,
Daniel He
Check out the November 2025 Power BI update to learn about new features.
Advance your Data & AI career with 50 days of live learning, contests, hands-on challenges, study groups & certifications and more!
| User | Count |
|---|---|
| 97 | |
| 71 | |
| 50 | |
| 47 | |
| 44 |