Is it possible to show task dependencies for the currently selected item/task in the report view? Source data is project.
Hi Team
I want to show the project tracker where my date is like below
Where Task 1 having dependency on Task 3 simlarily , Task 2 dependency on task 6
My requirement is i want measure or column which fatch the dates for Task 1 post the dependent Task Duedate or Revised date (task3) I.e my task start date should start from 29-oct-2021+1 date.
Please help me in the senerio
Thank you
Pradeep
Hi @nogi
It would be good if you can follow the link to provide more details
https://community.powerbi.com/t5/Community-Blog/How-to-Get-Your-Question-Answered-Quickly/ba-p/38490