Showing only Last Week progress

Hi!

I am using Power BI to show a project status. The data comes from Primavera P6.

 

One of the important measures is related to the %Plan vs %Actual for last week/month.

 

I have created this measure for %Actual_Last_Week:

 
%Actual_Last_Week = CALCULATE(
[%Actual_by_Category],filter(all('Project Calendar'[Date]),'Project Calendar'[Date]=MAX('NLU Distribution - ACTUAL'[Actual_Date])))
 
The measure works (almost) perfectly: 
 
jcarlos_0-1639908523624.png

As you can see, calculates the progress by week/by category.

 

However, when I use the measure in a general table...shows values from other weeks:

 

jcarlos_1-1639908690377.png

This value comes from August 2021:

 

jcarlos_2-1639908833234.png
I have two questions:
 
Why does my measure do this?
How could I fix it?
 
Regards,
 
 

 

1 ACCEPTED SOLUTION

Thanks @v-chenwuz-msft .

 

The relationship between my tables is like you are suggesting.

 

I've solved the issue by doing this:

 

%Actual_Last_Week =
VAR var_MAX_Date = calculate(MAX('NLU Distribution - ACTUAL'[Week_Rank]),ALL())
RETURN
CALCULATE(PROJECT[%Actual_by_Category],'Project Calendar'[Week_Rank]=var_MAX_Date,all('Project Calendar'[Week_Rank]))
 
Basically...declaring a VAR to define the MAX Date...removing ALL the filters to ensure MaxWeek it's the same for every category.
 
Many thanks for your support,
 
 

View solution in original post

5 REPLIES 5
jcarlos
Helper I
Helper I

Following @amitchandak advice...I've updated:

  • Transactional table: I've added a column 
    Week_Rank = RELATED('Project Calendar'[Week_Rank]), to "link" the transaction dates with the week number.
  • Project Calendar: I've added a column Week_Rank = RANKX(ALL('Project Calendar'),'Project Calendar'[Week_Start_Day],,ASC,Dense), to add the chronological week number to my calendar

And I've done some additional measures trying to show only the %Actual of last calendar week, instead of the %Actual of last week with data.

 

1) %Actual_Last_Week = CALCULATE(

DIVIDE([ACTUAL_SUM_NLU],[SUM_Weightage_By_Date]),'Project Calendar'[Week_Rank]=MAXA('NLU Distribution - ACTUAL'[Week_Rank]))
 
2)%Actual_Last_Week2 = IF(
SUM('NLU Distribution - ACTUAL'[NLU_Actual])=BLANK(),0,
calculate(
DIVIDE([ACTUAL_SUM_NLU],[SUM_Weightage_By_Date]),'Project Calendar'[Week_Rank]=MAXA('NLU Distribution - ACTUAL'[Week_Rank]))
)
 
In the end, the result is the same. It's like the measure "understand" as Last_Week, the latest week with information. 
 
Regards,

Hi @jcarlos ,

 

1 Set relationship cross filter direction is from 'Project Calendar' table to 'NLU Distribution - ACTUAL' table single and one to many.

 

2 try code like following :

 

 

%Actual_Last_Week =
CALCULATE(
    DIVIDE( [ACTUAL_SUM_NLU], [SUM_Weightage_By_Date] ),
    WEEKNUM( 'Project Calendar'[date] )
        = WEEKNUM( MAX( 'NLU Distribution - ACTUAL'[date] ) ) - 1
)

 

 

 

if does not work fine, please share pbix file without sensitive data.

 


Best Regards

Community Support Team _ chenwu zhu

 

If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

Thanks @v-chenwuz-msft .

 

The relationship between my tables is like you are suggesting.

 

I've solved the issue by doing this:

 

%Actual_Last_Week =
VAR var_MAX_Date = calculate(MAX('NLU Distribution - ACTUAL'[Week_Rank]),ALL())
RETURN
CALCULATE(PROJECT[%Actual_by_Category],'Project Calendar'[Week_Rank]=var_MAX_Date,all('Project Calendar'[Week_Rank]))
 
Basically...declaring a VAR to define the MAX Date...removing ALL the filters to ensure MaxWeek it's the same for every category.
 
Many thanks for your support,
 
 
amitchandak
Super User
Super User

@jcarlos , You need date/week table with Week rank

 

new columns needed in date table 
Week Start date = 'Date'[Date]+-1*WEEKDAY('Date'[Date],2)+1
Week End date = 'Date'[Date]+ 7-1*WEEKDAY('Date'[Date],2)
Week Rank = RANKX(all('Date'),'Date'[Week Start date],,ASC,Dense)
Week = WEEKNUM([Date],2)
year Week = if('Date'[Week Number]<10,'Date'[Year]*10 & 'Date'[Week Number],'Date'[Year]&'Date'[Week Number])
OR
Week Rank = RANKX(all('Date'),'Date'[Year Week],,ASC,Dense) //YYYYWW format

 

measures
This Week = CALCULATE(sum('Table'[Qty]), FILTER(ALL('Date'),'Date'[Week Rank]=max('Date'[Week Rank])))
Last Week = CALCULATE(sum('Table'[Qty]), FILTER(ALL('Date'),'Date'[Week Rank]=max('Date'[Week Rank])-1))

 

 

Power BI — Week on Week and WTD
https://medium.com/@amitchandak.1978/power-bi-wtd-questions-time-intelligence-4-5-98c30fab69d3
https://community.powerbi.com/t5/Community-Blog/Week-Is-Not-So-Weak-WTD-Last-WTD-and-This-Week-vs-La...
https://www.youtube.com/watch?v=pnAesWxYgJ8

Share with Power BI Enthusiasts: Full Power BI Video (20 Hours) YouTube
Microsoft Fabric Series 60+ Videos YouTube
Microsoft Fabric Hindi End to End YouTube

Many thanks, @amitchandak .

 

My date table already has Week_Start_Day and Week_Finish_Date.

 

I've followed your advice by adding the Week_Rank (which solves a big issue...because I didn't know how to add the chronological week number).

 

Regarding the measures: I have a 'NLU Distribution - ACTUAL' table, which has the historical transaction dates. 

 

In my original measure, the parameter I've used is

'Project Calendar'[Date]=MAX('NLU Distribution - ACTUAL'[Actual_Date])

 

Now...I don't get how to write the parameter using the Weel_Rank. Do I need to add a Week_Rank column in my 'NLU Distribution - ACTUAL' table?

 

jcarlos_0-1639982112051.png

'Project Calendar' table

 

jcarlos_1-1639982162248.png

'NLU Distribution - ACTUAL' table.

 

Regards,

 

 

 

 

Helpful resources

Announcements
FabCon and SQLCon Barcelona 2026

FabCon & SQLCon – Barcelona 2026

Join us in Barcelona for FabCon and SQLCon, the Fabric, Power BI, SQL, and AI community event. Save €200 with code FABCMTY200.

60 days of Data Days Carousel

Data Days 2026

Join Data Days 2026: 60 days of free live/on-demand sessions, challenges, study groups, and certification opportunities.

Power BI DataViz World Championships carousel

Power BI DataViz World Championships - June 2026

A new Power BI DataViz World Championship is coming this June! Don't miss out on submitting your entry.

Top Solution Authors