Skip to main content
cancel
Showing results for 
Search instead for 
Did you mean: 

Earn a 50% discount on the DP-600 certification exam by completing the Fabric 30 Days to Learn It challenge.

Reply
colourfullife
Post Partisan
Post Partisan

Schedule duration analysis

Hi

 

1) i have a plan dates of Start and Finish for my project activities.

2) i have 2 files. revision1 and 2.

3) want to compare how much these 2 files different.

4) which visualization would be pefect to analyze the data??

 

I have a report to see schedule duration using one of them.  Tool.PNG

but this visulation only put one date in Start date and finish date...?

 

any good idea?

thanks,

3 REPLIES 3
TeigeGao
Solution Sage
Solution Sage

Hi @colourfullife ,

According to your description, my understanding is that you want to mark the items which are different between versions in the visual, actually, many visual can do that, it depends on your requirement.

We can use a matrix to display it:

Assume that we have two tables like below:

version2version2version1version1

Then we can create two measure to judge if the data is different:

Measure = IF(MIN(version1[Finish])<>MIN(version2[Finish]),1,0)
Measure 2 = IF(MIN(version1[Start]) <> MIN(version2[Start]),1,0)

The we can drag the data fields to matrix, then set the conditional formatting for the matrix visual:

hU5O0wqYGQ.png

The result will like below:

PBIDesktop_5SH19l5SEx.png

Best Regards,

Teige

thanks very much. could you please share the file that you created?

Also, Is there any way to use this visulization Tool.PNG to do same activity that you did?

 

thanks,

Hi @colourfullife ,

Could you please tell us what's the visual do you want?

Best Regards,

Teige

Helpful resources

Announcements
RTI Forums Carousel3

New forum boards available in Real-Time Intelligence.

Ask questions in Eventhouse and KQL, Eventstream, and Reflex.

LearnSurvey

Fabric certifications survey

Certification feedback opportunity for the community.