Restrict the data load

Hi all,

 

I need your help in restricting the data while loading into power bi.I want the restrict the the uncompleted weeks data to be restircted to load. For e.g., If I have data till 28-jan-2021 I want the data to be loaded till 24-Jan-2021 since the week has been completed till 24-jan-2021 and 28 is in between the week of 25-jan to 31-jan which is not completed.The week starts from Mon-Sun.

 

Thanks in advance,

1 ACCEPTED SOLUTION
Icey
Community Support
Community Support

Hi @Anonymous ,

 

There is one option in incremental refresh in Power BI - Only refresh complete periods.

 

In your scenario, if could, try to set as below. When you set the incremental range to 7 days and schedule the refresh to run on the 1st day of the week. With this option checked, it would for example refresh weekly data on Sunday.

 

incremental.JPG

 

 

Best Regards,

Icey

 

If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

4 REPLIES 4
amitchandak
Super User
Super User

@Anonymous , is it for a refresh or incremental load.

 

You can use query parameters

https://www.biinsight.com/power-bi-desktop-query-parameters-part-1/

Share with Power BI Enthusiasts: Full Power BI Video (20 Hours) YouTube
Microsoft Fabric Series 60+ Videos YouTube
Microsoft Fabric Hindi End to End YouTube
Anonymous
Not applicable

Hi @amitchandak ,

It for a refresh

 

Icey
Community Support
Community Support

Hi @Anonymous ,

 

There is one option in incremental refresh in Power BI - Only refresh complete periods.

 

In your scenario, if could, try to set as below. When you set the incremental range to 7 days and schedule the refresh to run on the 1st day of the week. With this option checked, it would for example refresh weekly data on Sunday.

 

incremental.JPG

 

 

Best Regards,

Icey

 

If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

@Anonymous , I think you have to explore Query parameters

Share with Power BI Enthusiasts: Full Power BI Video (20 Hours) YouTube
Microsoft Fabric Series 60+ Videos YouTube
Microsoft Fabric Hindi End to End YouTube

Helpful resources

Announcements
Join our Fabric User Panel

Join our Fabric User Panel

Share feedback directly with Fabric product managers, participate in targeted research studies and influence the Fabric roadmap.

February Power BI Update Carousel

Power BI Monthly Update - February 2026

Check out the February 2026 Power BI update to learn about new features.

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.