Project Management Report - Task Completion

Hi All,

 

Go easy, this is my first ever post!

 

I need to be able to calculated expected task completion percentage based on TODAY. Eg on Day 3 of a 10 day task, it should be 30% complete in theory. I need a fomula that calculates the current expected completion that changes on a day to day basis? Once I have this I can then compare with actual completion and add to my RAG rating.

 

Many thanks

 

1 ACCEPTED SOLUTION

Hi @Wharfey ,

 

You can create column like DAX below.

 

expected_completion %=DIVIDE(DATEDIFF( [start_date], TODAY(), DAY), DATEDIFF( [start_date], [finish_date], DAY))

 

Best Regards,

Amy

 

Community Support Team _ Amy

If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

3 REPLIES 3
Tahreem24
Super User
Super User

@Wharfey , Welcome to Power BI Community!

 

You want something like below Screen shot? if yes so use the below Measure and set it data format to %.

Task Completed = Sum('Table'[Day])/CALCULATE(sum('Table'[Day]),ALL('Table'[Day]))
 
Capture.JPG
 
Please don't forget to hit THUMBS UP and Accept this as a solution if it helps you!
Don't forget to give thumbs up and accept this as a solution if it helped you!!!

Please take a quick glance at newly created dashboards : Restaurant Management Dashboard , HR Analytics Report , Hotel Management Report, Sales Analysis Report , Fortune 500 Companies Analysis , Revenue Tracking Dashboard

Hi Tahreem

 

This is the kind of table view I'm after (below) so essentially all I need is a formula to calculate column E based on the TODAY() function that counts back to the start date and calculates what the percentage completion should be as of the current date. I will then use DAX to determine the Task_Health rating.

 

Project management expected completion.JPG

 

thanks again.

 
 
 

Hi @Wharfey ,

 

You can create column like DAX below.

 

expected_completion %=DIVIDE(DATEDIFF( [start_date], TODAY(), DAY), DATEDIFF( [start_date], [finish_date], DAY))

 

Best Regards,

Amy

 

Community Support Team _ Amy

If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

Helpful resources

Announcements
Fabric Data Days Carousel

Fabric Data Days

Advance your Data & AI career with 50 days of live learning, contests, hands-on challenges, study groups & certifications and more!

October Power BI Update Carousel

Power BI Monthly Update - October 2025

Check out the October 2025 Power BI update to learn about new features.

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.

Top Solution Authors