Project Completion Analysis
Hello! I am trying to build a calculation that will give me the avg days between each component of the project process. For example: In the below excel file I have project ID 1 and I want to konw th...
v-yuta-msft
8 years agoCommunity Support
Hi nmck86,
What's your expected result? Please provide a sample of your expect result
Regards,
Jimmy Tao
nmck86
8 years agoPost Patron
Sure, I would like to see the days between each status so for project 1 there are 2 days between the WAPPR status and the Initiated status. There are also 26 days between the start of the project and the completion of the project. This is what I was trying to get to show up. Let me know if you have other questions.