Forum Discussion

lisampederson's avatar
8 years ago
Solved

Progress Curve Visualization with Percent Complete and Forecast Complete

Hello,

 

I'm having difficulties finding a visualization that would work for progress curves.  I keep getting the axis to show something above 1 (or 100%) which I don't understand why that's happening.  See screenshots below.  I'd also like to see a few bars to represent months instead of a sum of all the months in the year.  My data is by month. 

 

I'd like to just simply show planned % complete, actual % complete, and then forecast % complete if there is no actual.

 

I also would like to filter the visualization by project.  Each tab in my data is by project and each tab shows the column project and says "project a/b/c".  Will this work?

 

Any advise would be appreciated!  Thank you.

 

 

Lisa

 

3 Replies