Hi guys!
I am suffering with a performance issue for a measure.
It is derived from several others, so I'll paste all the ones that are calculated for the last one to exist.
All the previous are not affecting the performance when brought in a table (for instance).
Do you have any advices to save processing, maybe using different syntaxes...
This is what I did to calculate the average use for the next 30 days of every item
Then this is what I did to find out the target stock value for each one
I then do a SUMX against the unit values
This is how I calculate what I current have in Stock
And finally this is the Measure that is causing the performance impact, when I have to calculate the Excess Stock existent based on all the previous ones
Solved! Go to Solution.
@Anonymous,
You can use variable to avoid double calculation in your measure:
Excess Stock =
VAR result = [Valid Stock Value] - [TargetStockValue] - [No Future Use]
RETURN
IF ( result < 0, 0, result )
@Anonymous,
Same principle applies. You want to avoid repeating measure because it calculates every time you mention it. Use variable so the result is stored in the memory
Stock OK =
VAR validStock = [Valid Stock Value]
VAR targetStock = [TargetStockValue]
RETURN
SWITCH ( TRUE (); validStock >= targetStock; targetStock; validStock )
@Anonymous,
You can use variable to avoid double calculation in your measure:
Excess Stock =
VAR result = [Valid Stock Value] - [TargetStockValue] - [No Future Use]
RETURN
IF ( result < 0, 0, result )
@Anonymous
This one is still a bit slow, though... any ideas about it?
@Anonymous,
Same principle applies. You want to avoid repeating measure because it calculates every time you mention it. Use variable so the result is stored in the memory
Stock OK =
VAR validStock = [Valid Stock Value]
VAR targetStock = [TargetStockValue]
RETURN
SWITCH ( TRUE (); validStock >= targetStock; targetStock; validStock )
@Anonymous
@Anonymous wrote:@Anonymous,
You can use variable to avoid double calculation in your measure:
Excess Stock = VAR result = [Valid Stock Value] - [TargetStockValue] - [No Future Use] RETURN IF ( result < 0, 0, result )
Awesome! This reduced the calculation time from 4 minutes to 10 secs. Thanks!
Share feedback directly with Fabric product managers, participate in targeted research studies and influence the Fabric roadmap.
Check out the February 2026 Power BI update to learn about new features.
| User | Count |
|---|---|
| 54 | |
| 47 | |
| 39 | |
| 16 | |
| 15 |
| User | Count |
|---|---|
| 83 | |
| 71 | |
| 39 | |
| 29 | |
| 27 |