P6-Gantt Chart Visual
- 24 days ago
tharunkumarRTK
thank you for the answer, at the following link I saved: PBI test- E_PM_KPIs_DONA the file on which I tried to build the Design Gantt
- excel of the data needed to build it
- original example of the visual
so what i will need is something that show:
1st level
> Design Packages (list is in the file E_SCHEDULE_P6_PROGRAMME sheet Design Packages but I have also already marged in the models)
2nd level >
Baseline time line
Actual time line
Forecast time line
P6 Activity (milestone taking the end date from E_SCHEDULE_P6_PROGRAMME sheet PBI column BL finish)
3rd level
> Successors (milestone taking start date from E_SCHEDULE_P6_PROGRAMME sheet PBI column Bl Start)
thanks
Dropje
Hi Dropje
Try to replicate what the third-party visual is doing. It uses three tables: a Level table, a WBS Code table, and a Task table. Identify how you can transform your existing tables into these three tables, then replicate their columns and relationships. Once you've done that, you should be able to create the same visual.