Newbie trying to figure out how to structure data for a Gantt chart

I have some tables I need to process in order to create a Gannt chart. I wish to sort the tasks/roles per person. The challenge is that I have one table (A) that includes the dates for the Gantt chart and the id of the project managers. The same persons can also be assigned projects without leading them. This is stored in another table (B) with reference to the file that contains project data (A).

When I build this in Microsoft Acess I simply created a query that created a table containing ProjectID, PersonId and Role ("Lead" or "Assisting"). I then linked this table to others to get the additional data I needed. Can this be done in Power BI or can I get the result in any other way?

The "resource" column in the Gantt chart would like something below (and the the Gantt bars would follow to the right):

 

Name      Role

Mike P     Lead

                Assisting

Peter N    Lead

                Lead

                Assisting

1 ACCEPTED SOLUTION
AmiraBedh
Super User
Super User

 

In PQ, use  "Append Queries"  to combine your tables. You should have a table where each row contains a ProjectID, PersonID, Role (Lead or Assisting), Start Date, and End Date.

 

Then create a calculated column :

 

Resource = TableA[PersonID] & " - " & TableA[Role]

 

Then create your Gantt chart.

 


Proud to be a Power BI Super User !

Microsoft Community : https://docs.microsoft.com/en-us/users/AmiraBedhiafi
Linkedin : https://www.linkedin.com/in/amira-bedhiafi/
StackOverflow : https://stackoverflow.com/users/9517769/amira-bedhiafi
C-Sharp Corner : https://www.c-sharpcorner.com/members/amira-bedhiafi
Power BI Community :https://community.powerbi.com/t5/user/viewprofilepage/user-id/332696

View solution in original post

1 REPLY 1
AmiraBedh
Super User
Super User

 

In PQ, use  "Append Queries"  to combine your tables. You should have a table where each row contains a ProjectID, PersonID, Role (Lead or Assisting), Start Date, and End Date.

 

Then create a calculated column :

 

Resource = TableA[PersonID] & " - " & TableA[Role]

 

Then create your Gantt chart.

 


Proud to be a Power BI Super User !

Microsoft Community : https://docs.microsoft.com/en-us/users/AmiraBedhiafi
Linkedin : https://www.linkedin.com/in/amira-bedhiafi/
StackOverflow : https://stackoverflow.com/users/9517769/amira-bedhiafi
C-Sharp Corner : https://www.c-sharpcorner.com/members/amira-bedhiafi
Power BI Community :https://community.powerbi.com/t5/user/viewprofilepage/user-id/332696

Helpful resources

Announcements
FabCon Global Hackathon Carousel

FabCon Global Hackathon

Join the Fabric FabCon Global Hackathon—running virtually through Nov 3. Open to all skill levels. $10,000 in prizes!

September Power BI Update Carousel

Power BI Monthly Update - September 2025

Check out the September 2025 Power BI update to learn about new features.

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.

Top Solution Authors
Top Kudoed Authors