NETWORKDAYS inside PowerBI

There are two columns, Void Start and Due Date, I would like to work out the number of working days between the two days.

I've tried to use the following formula shown here (by @Greg_Deckler ), but I can't seem to get it to work.

This is the code for my situation (created it as a measure):

NetWorkDays = 
VAR Calendar1 = CALENDAR(MAX('Voids Data'[Void Start]),MAX('Voids Data'[Due Date (corrected)]))
VAR Calendar2 = ADDCOLUMNS(Calendar1,"WeekDay",WEEKDAY([Date],2))
RETURN COUNTX(FILTER(Calendar2,[WeekDay]<6),[Date])


It's accepted by PowerBI, but when I throw it into a table visualisation (this visualisation has two columns, one is void start date, the other is due date), I get the following error:



https://imgur.com/a/eCWRH4P
Please help.

1 ACCEPTED SOLUTION
raeesgillani
Advocate I
Advocate I

So I kept playing around with different solutions but the original solution provided by @Greg_Deckler seemed to work once I removed null values from my data and then made the extreme values zero:

VAR Calendar1 = CALENDAR(MIN('Voids Data'[Start]),MIN('Voids Data'[End]))
VAR Calendar2 = ADDCOLUMNS(Calendar1,"WeekDay",WEEKDAY([Date],2))
RETURN IF(COUNTX(FILTER(Calendar2,[WeekDay]<6),[Date])>1000,0,COUNTX(FILTER(Calendar2,[WeekDay]<6),[Date]))

View solution in original post

3 REPLIES 3
raeesgillani
Advocate I
Advocate I

So I kept playing around with different solutions but the original solution provided by @Greg_Deckler seemed to work once I removed null values from my data and then made the extreme values zero:

VAR Calendar1 = CALENDAR(MIN('Voids Data'[Start]),MIN('Voids Data'[End]))
VAR Calendar2 = ADDCOLUMNS(Calendar1,"WeekDay",WEEKDAY([Date],2))
RETURN IF(COUNTX(FILTER(Calendar2,[WeekDay]<6),[Date])>1000,0,COUNTX(FILTER(Calendar2,[WeekDay]<6),[Date]))

Hi raeesgillani,

Could you please tell us if your problem has been solved? If you have any problem, please feel free to tell me.

Best Regards,

Teige

Yes the issue was resolved, thank you for the check 🙂

Helpful resources

Announcements
November Carousel

Fabric Community Update - November 2024

Find out what's new and trending in the Fabric Community.

Live Sessions with Fabric DB

Be one of the first to start using Fabric Databases

Starting December 3, join live sessions with database experts and the Fabric product team to learn just how easy it is to get started.

Las Vegas 2025

Join us at the Microsoft Fabric Community Conference

March 31 - April 2, 2025, in Las Vegas, Nevada. Use code MSCUST for a $150 discount! Early Bird pricing ends December 9th.

Nov PBI Update Carousel

Power BI Monthly Update - November 2024

Check out the November 2024 Power BI update to learn about new features.