NETWORKDAYS inside PowerBI

There are two columns, Void Start and Due Date, I would like to work out the number of working days between the two days.

I've tried to use the following formula shown here (by @Greg_Deckler ), but I can't seem to get it to work.

This is the code for my situation (created it as a measure):

NetWorkDays = 
VAR Calendar1 = CALENDAR(MAX('Voids Data'[Void Start]),MAX('Voids Data'[Due Date (corrected)]))
VAR Calendar2 = ADDCOLUMNS(Calendar1,"WeekDay",WEEKDAY([Date],2))
RETURN COUNTX(FILTER(Calendar2,[WeekDay]<6),[Date])


It's accepted by PowerBI, but when I throw it into a table visualisation (this visualisation has two columns, one is void start date, the other is due date), I get the following error:



https://imgur.com/a/eCWRH4P
Please help.

1 ACCEPTED SOLUTION
raeesgillani
Advocate I
Advocate I

So I kept playing around with different solutions but the original solution provided by @Greg_Deckler seemed to work once I removed null values from my data and then made the extreme values zero:

VAR Calendar1 = CALENDAR(MIN('Voids Data'[Start]),MIN('Voids Data'[End]))
VAR Calendar2 = ADDCOLUMNS(Calendar1,"WeekDay",WEEKDAY([Date],2))
RETURN IF(COUNTX(FILTER(Calendar2,[WeekDay]<6),[Date])>1000,0,COUNTX(FILTER(Calendar2,[WeekDay]<6),[Date]))

View solution in original post

3 REPLIES 3
raeesgillani
Advocate I
Advocate I

So I kept playing around with different solutions but the original solution provided by @Greg_Deckler seemed to work once I removed null values from my data and then made the extreme values zero:

VAR Calendar1 = CALENDAR(MIN('Voids Data'[Start]),MIN('Voids Data'[End]))
VAR Calendar2 = ADDCOLUMNS(Calendar1,"WeekDay",WEEKDAY([Date],2))
RETURN IF(COUNTX(FILTER(Calendar2,[WeekDay]<6),[Date])>1000,0,COUNTX(FILTER(Calendar2,[WeekDay]<6),[Date]))

Hi raeesgillani,

Could you please tell us if your problem has been solved? If you have any problem, please feel free to tell me.

Best Regards,

Teige

Yes the issue was resolved, thank you for the check 🙂

Helpful resources

Announcements
Las Vegas 2025

Join us at the Microsoft Fabric Community Conference

March 31 - April 2, 2025, in Las Vegas, Nevada. Use code MSCUST for a $150 discount!

Dec Fabric Community Survey

We want your feedback!

Your insights matter. That’s why we created a quick survey to learn about your experience finding answers to technical questions.

ArunFabCon

Microsoft Fabric Community Conference 2025

Arun Ulag shares exciting details about the Microsoft Fabric Conference 2025, which will be held in Las Vegas, NV.

December 2024

A Year in Review - December 2024

Find out what content was popular in the Fabric community during 2024.