Good afternoon
I'm new and I have a problem that I can't solve:
I have a table of facility data, in which I have the start, end and service days dates for each installation (assemblies). I want to count the services per day, but since the duration of the installation is >1 day, it no longer tells me that the next day that installer is busy, because it counts only the dates that appear in the table.
Something like that
| Service | start date | days of service | end date |
| A | 29/03/2021 | 2 | 30/03/2021 |
| B | 29/03/2021 | 3 | 31/03/2021 |
| C | 30/03/2021 | 3 | 01/04/2021 |
| D | 30/03/2021 | 2 | 31/03/2021 |
| E | 30/03/2021 | 4 | 02/04/2021 |
| F | 30/03/2021 | 1 | 30/03/2021 |
| G | 31/03/2021 | 2 | 01/04/2021 |
| H | 01/04/2021 | 2 | 02/04/2021 |
| I | 02/04/2021 | 3 | 04/04/2021 |
| J | 03/04/2021 | 1 | 03/04/2021 |
On the 31st/03rd I would have to show up that I have 5 installations in progress, but only counts 1, for its start date.
In excel is very simple, I make a macro that inserts me an extra row with the same data but changing the service date and ready, but the data automatically reaches me power bi and I didn't want to have to go through excel.
Could someone help me?
A greeting and thank you very much in advance
Solved! Go to Solution.
Hi @Syndicate_Admin ,
You can create a dim_date table for slicer:
Dim_Date = CALENDARAUTO()
Then use the following measure to show up installations in progress:
service in progress = CALCULATE(COUNT('Table'[Service]),FILTER('Table','Table'[start date]<=SELECTEDVALUE(Dim_Date[Date])&&'Table'[end date]>=SELECTEDVALUE(Dim_Date[Date])))
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Best Regards,
Dedmon Dai
Hi @Syndicate_Admin ,
You can create a dim_date table for slicer:
Dim_Date = CALENDARAUTO()
Then use the following measure to show up installations in progress:
service in progress = CALCULATE(COUNT('Table'[Service]),FILTER('Table','Table'[start date]<=SELECTEDVALUE(Dim_Date[Date])&&'Table'[end date]>=SELECTEDVALUE(Dim_Date[Date])))
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Best Regards,
Dedmon Dai
Thanks a lot! This is extremely what I needed!
It's perfect!
Vote for your favorite vizzies from the Power BI World Championship submissions!
If you love stickers, then you will definitely want to check out our Community Sticker Challenge!
Check out the January 2026 Power BI update to learn about new features.
| User | Count |
|---|---|
| 64 | |
| 51 | |
| 46 | |
| 23 | |
| 19 |
| User | Count |
|---|---|
| 135 | |
| 110 | |
| 50 | |
| 31 | |
| 29 |