Matrix as Gantt Chart with multiple Starting and End Dates for same row

Dear PBI Community,
let me explain my problem:

I do have 2 Tables: 
1. Is Containing Projects with Start and End Dates (which i can show and have no problems with)

2. Is Containing the project phases assigned to a person again with Start and End Dates

you can see by the following screenshot (ProjectStart and EndDate shown as LookUp here)

T800_1-1637865099594.png

 

The Matrix Gantt Chart looks like this right now (pls ignore pink and light pink cells):

T800_2-1637865304391.png

T800_3-1637865910563.png

 

You see that i am only able to show in darkblue colour the earliest (MIN) and the last (MAX) date entered. BUT  i am missing the phase in August (row 3) since it is in the middle. My question is: How can i show ALL entered phases DateRanges in the same row?

Project + Phase + Responsible are the same but differ from Phase Start and Phase End Dates.


Here my DAX Measure i am using and giving conditional formatting on:


CF Gantt =
// Projects

VAR StartDate =
CALCULATE(
MIN('Total_Report'[StartDate]),
REMOVEFILTERS(Dim_M_Calendar)
)
VAR EndDate =
CALCULATE(
MIN('Total_Report'[EndDate]),
REMOVEFILTERS(Dim_M_Calendar)
)
VAR ProjectPeriod =
MIN(Dim_M_Calendar[Date])>=StartDate && MIN(Dim_M_Calendar[Date]) <= EndDate
VAR Result =
IF(ProjectPeriod,1,0)

// ProjectPHASES

VAR StartDatePhaseMIN =
CALCULATE(
MIN('Total_Report'[StartDatePhase - Month]),
REMOVEFILTERS(Dim_M_Calendar)
)
VAR EndDatePhaseMIN =
CALCULATE(
MIN('Total_Report'[EndDatePhase - Month]),
REMOVEFILTERS(Dim_M_Calendar)
)
VAR StartDatePhaseMAX =
CALCULATE(
MAX('Total_Report'[StartDatePhase - Month]),
REMOVEFILTERS(Dim_M_Calendar)
)
VAR EndDatePhaseMAX =
CALCULATE(
MAX('Total_Report'[EndDatePhase - Month]),
REMOVEFILTERS(Dim_M_Calendar)
)

VAR PhasePeriodMIN = CALCULATE(
MIN(Dim_M_Calendar[Date])>=StartDatePhaseMIN && MIN(Dim_M_Calendar[Date]) <= EndDatePhaseMIN)
VAR PhasePeriodMAX = CALCULATE(
MAX(Dim_M_Calendar[Date])>=StartDatePhaseMAX && MAX(Dim_M_Calendar[Date]) <= EndDatePhaseMAX)
VAR Result2 =
IF(PhasePeriodMIN || PhasePeriodMAX,1,0)

// Absences

VAR StartDateAbsenceMIN =
CALCULATE(
MIN('Total_Report'[StartDateUrlaub - Month]),
REMOVEFILTERS(Dim_M_Calendar)
)
VAR EndDateAbsenceMIN =
CALCULATE(
MIN('Total_Report'[EndDateUrlaub - Month]),
REMOVEFILTERS(Dim_M_Calendar)
)
VAR StartDateAbsenceMAX =
CALCULATE(
MAX('Total_Report'[StartDateUrlaub - Month]),
REMOVEFILTERS(Dim_M_Calendar)
)
VAR EndDateAbsenceMAX =
CALCULATE(
MAX('Total_Report'[EndDateUrlaub - Month]),
REMOVEFILTERS(Dim_M_Calendar)
)
VAR AbsencePeriodMIN =
MIN(Dim_M_Calendar[Date])>=StartDateAbsenceMIN && MIN(Dim_M_Calendar[Date]) <= EndDateAbsenceMIN
VAR AbsencePeriodMAX =
MAX(Dim_M_Calendar[Date])>=StartDateAbsenceMAX && MAX(Dim_M_Calendar[Date]) <= EndDateAbsenceMAX

VAR Result3 =
IF(AbsencePeriodMIN || AbsencePeriodMAX,3,0)

//Zusammenfassen der Resultate

VAR FinalResult = Result + Result2 + Result3
Return
FinalResult
 

*******************************


You can ignore the absences (pink ones) since it is exactly the same problem like with the phases.

 

Thanks in advance and kind regards

 

 



 

1 REPLY 1
MFelix
Super User
Super User

Hi @Anonymous ,

 

To what I can see from your data the 3 rows that you present are all from the same projcet/phase so when you make a matrix grouping by project/phase and pick up the maximum (or minimum) from 3 rows you will get only a single value, in this case the 1st of January for the Phase start and the 31 of december for the phase end.

 

In this case you need to make a different comparision in order to get the phase in a different colour.

 

Can you please share a mockup data or sample of your PBIX file. You can use a onedrive, google drive, we transfer or similar link to upload your files.

If the information is sensitive please share it trough private message.


Regards

Miguel Félix


Did I answer your question? Mark my post as a solution!

Proud to be a Super User!

Check out my blog: Power BI em Português



Helpful resources

Announcements
September Power BI Update Carousel

Power BI Monthly Update - September 2025

Check out the September 2025 Power BI update to learn about new features.

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.

Top Solution Authors