Negral75
Regular Visitor

KPI Linear approximation forecast

Hey guys !

 

I'm working on my KPI report and I've come across a problem. I need to create a curve of tasks progression, but I need a reference progression too. I group everything by week, so if you have a 6 weeks tasks, it'll only be to 100% at the end week. What I want is to create a linear approximation of this progression.

 

For example, if you have that 6 weeks task starting week 24, it would go like :

24 : 0% ; 25 : 17% ; 26; 33% ; 27 : 50% ; 28 : 67%; 29 : 83% ; 30 : 100%

 

But what I have now it's :

 

24 to 29 : 0% ; 30:100%

 

I already calculated the coefficient to make the approximation : 1.jpg

 

 I have no clue about how to create the approximation I want for all the tasks, I don't manage to apply it to even 1 !

 

Any help is welcome !

 

 

1 REPLY 1
Anonymous
Not applicable

@Negral75,

Which column is week column in the above screenshot? And what fields do you use to calculate coefficient? Please help to share raw data of the table that can be copied so that we can test and provide you appropriate DAX.

Regards,
Lydia

Helpful resources

Announcements
Join our Fabric User Panel

Join our Fabric User Panel

Share feedback directly with Fabric product managers, participate in targeted research studies and influence the Fabric roadmap.

March Power BI Update Carousel

Power BI Community Update - March 2026

Check out the March 2026 Power BI update to learn about new features.