Hi,

 

I've loaded a lot of progress steps from a Sharepoint list. In Power Query I've created columns to have a column for each step to see if it's completed or not (only 2 phases are displayed for now for demo)

 

tabel.png

Now I want to visualize this in this way: where red is completed. The not completed steps can be blank or a different color is also fine. 

 

visual.png

 

What is the best way to achive this?

1 ACCEPTED SOLUTION
Anonymous
Not applicable

  1. Use matrix visual to satiesfy your requirment
  2. matrix visual will give you conditional formatting option in formate section where you can set the background colors depends on condition.

View solution in original post

2 REPLIES 2
Anonymous
Not applicable

  1. Use matrix visual to satiesfy your requirment
  2. matrix visual will give you conditional formatting option in formate section where you can set the background colors depends on condition.

Thanks @Anonymous thanks for your hint! I needed to change the values completed / not completed into 1,0 first.

 

 

Helpful resources

Announcements
November Power BI Update Carousel

Power BI Monthly Update - November 2025

Check out the November 2025 Power BI update to learn about new features.

Fabric Data Days Carousel

Fabric Data Days

Advance your Data & AI career with 50 days of live learning, contests, hands-on challenges, study groups & certifications and more!

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.

Top Solution Authors
Top Kudoed Authors