Skip to main content
cancel
Showing results for 
Search instead for 
Did you mean: 

To celebrate FabCon Vienna, we are offering 50% off select exams. Ends October 3rd. Request your discount now.

Reply
her
Helper III
Helper III

How to distinct column Row in Maq Gantt Chart

Hi all,

how to distinct column row in MAQ Gantt Chart Visualization..

repeated rows as to distinct 

timeline1.JPG

if anyone find the solution  please let me know 

 

thanks and regards 

herwin

7 REPLIES 7
MAQSupport
Solution Supplier
Solution Supplier

Hello @her ,

 

We tested the visual with your dataset and observed the following:

Currently, three rows are displayed for Change Readiness Framework as there are 3 distinct values in ‘Activity’ column for this category.

To have distinct column row for Initiative ‘Change Readiness Framework’, you can remove the ‘Activity’ column dragged in Category.

 

On removing ‘Activity’ column, there will be a single distinct row as shown below:gantt.png

Please feel free to contact us at support@maqsoftware.com for any issues.

 

Hi @MAQSupport  

Thanks for your response but initiative name must distinct only at the same time only one initiative name  show..

 

timeline2.JPG

here Agile training program  two is there but we want to show one that is my requirement.

 

thanks and regards

Herwin

Anonymous
Not applicable

@her - Does it work if you remove Activities?

hi @Anonymous  

its not working removed after Activity...

thanks regards

herwin

hi, @her 

I think there must be other fields could not be aggregated in this chart.

So the best way to check it is:

Copy this visual and then change the duplicate visual to table visual

Now use a slicer to filter the Initiatives is "change Readiness Framework" to check which field isn't aggregated.

For example:

This is my simple example

5.JPG

Then I COPY it and then change it to table visual

6.JPG

Now we find that there is a field "Milestone" could not be aggregated which leads to this problem.

Then we remove field "Milestone" for Maq Gantt Chart and it meets your requirement.

7.JPG

 

If you still have the problem, please share a simple sample pbix file for us to have a test.

 

Best Regards,

Lin

Community Support Team _ Lin
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

Hi @v-lili6-msft ,

Thanks for your response. However as per our requirement, we need all the fields specified in our example in the report.

 

Thanks,

Herwin

 

hi, @her 

Because there are one or more fields couldn't be aggregated. so they will be shown by multiple lines.

Unless you remove it by the way i have provided above.

 

Best Regards,

Lin

Community Support Team _ Lin
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

Helpful resources

Announcements
September Power BI Update Carousel

Power BI Monthly Update - September 2025

Check out the September 2025 Power BI update to learn about new features.

August 2025 community update carousel

Fabric Community Update - August 2025

Find out what's new and trending in the Fabric community.

Top Solution Authors
Top Kudoed Authors