I had a problem, how do I filter status close in 2016, 2017 and so on where I want to close it appeared in 2017, while in 2016 it did not appear. if the power of bi could do that?
Project 2016:
Delay = 18
On Schedule = 7
Close = 52
Project 2017:
Close = 1
New = 3
On Schedule = 23
Project 2018:
On Schedule = 1
Based on your description, I'm still not clear about your requirement. Do you want to filter out projects which are closed in 2017 and started in 2016? Can you share some sample raw data?
Regards,
@v-sihou-msft sorry late for reply your massage,
I've found a way to do that, and thank you for responding to my question. 🙂
| User | Count |
|---|---|
| 23 | |
| 20 | |
| 19 | |
| 19 | |
| 10 |
| User | Count |
|---|---|
| 53 | |
| 52 | |
| 41 | |
| 37 | |
| 32 |