Hi there,
I'd like to copy a page from one report to another report.
I see that this wasn't available 2 years ago: https://community.powerbi.com/t5/Desktop/Copy-Move-page-to-other-report/m-p/380115
Is there a way to do this now?
Solved! Go to Solution.
@KamKam , Yes, it works.
Try to open the View->selection section, select all components (press shift to do this quicker) and copy it to a new report.
Hi @KamKam ,
You can copy a page by selecting all items on that page (ctr + a) and pasting them into a second report.
The limitation here is that bookmarks will not be copied. If any columns or measures are missing in the new report, you will receive an error that needs to be fixed.
Thanks @lkalawski,
Are you sure that this works? Because I have tried that a couple times now and it just isn't working.
@KamKam , Yes, it works.
Try to open the View->selection section, select all components (press shift to do this quicker) and copy it to a new report.
Thanks @lkalawski,
I ended up copying each component one at a time. The ctrl+a method didn't work for me.
March 31 - April 2, 2025, in Las Vegas, Nevada. Use code MSCUST for a $150 discount!
Check out the February 2025 Power BI update to learn about new features.
If you love stickers, then you will definitely want to check out our Community Sticker Challenge!
User | Count |
---|---|
84 | |
69 | |
68 | |
39 | |
37 |