raq3
Frequent Visitor

How can I create a graph with burn hours, estimated hours, and over hours?

Hi everyone, 

 

I am trying to create a graph with all the hours our department already used, the estimated hours we had in mind, and the over hours. However, this is summing all the hours instead of showing the "progress". I want to create a graph to see how many hours were already used (either less or more than estimated). Can you help me with this, please?

 

hours cons.PNG

 

 

Thank you

1 ACCEPTED SOLUTION
Ritaf1983
Super User
Super User

If I get it right, the goal is to follow up on estimates.
The graph in the picture is less effective at first.
Consider using the table  graph as in the picture:
Using this method, the differences can be compared in the most accurate way

Ritaf1983_0-1683175078533.png

This method requires you to calculate the following measures:

TotalBurned = sum('Table'[Burned])
TotalEstimated = sum('Table'[Estimated])
TotalGap = [TotalEstimated]-[TotalBurned]
 
If there is still a desire for a stacked graph.
Only applicable in cases where there are no exceptions.
Since it is not possible to influence thegaps between the points, it is more difficult to read.
You can Create Some Thing like This:
Ritaf1983_1-1683175873655.png

In order to visualize progress, you should include the following measures in the graph:
estimated
and
Gap
(Based on the calculation I provided earlier)
Link to Sample file 
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.



Regards,
Rita Fainshtein | Microsoft MVP
https://www.linkedin.com/in/rita-fainshtein/
Blog : https://www.madeiradata.com/profile/ritaf/profile

View solution in original post

1 REPLY 1
Ritaf1983
Super User
Super User

If I get it right, the goal is to follow up on estimates.
The graph in the picture is less effective at first.
Consider using the table  graph as in the picture:
Using this method, the differences can be compared in the most accurate way

Ritaf1983_0-1683175078533.png

This method requires you to calculate the following measures:

TotalBurned = sum('Table'[Burned])
TotalEstimated = sum('Table'[Estimated])
TotalGap = [TotalEstimated]-[TotalBurned]
 
If there is still a desire for a stacked graph.
Only applicable in cases where there are no exceptions.
Since it is not possible to influence thegaps between the points, it is more difficult to read.
You can Create Some Thing like This:
Ritaf1983_1-1683175873655.png

In order to visualize progress, you should include the following measures in the graph:
estimated
and
Gap
(Based on the calculation I provided earlier)
Link to Sample file 
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.



Regards,
Rita Fainshtein | Microsoft MVP
https://www.linkedin.com/in/rita-fainshtein/
Blog : https://www.madeiradata.com/profile/ritaf/profile

Helpful resources

Announcements
November Power BI Update Carousel

Power BI Monthly Update - November 2025

Check out the November 2025 Power BI update to learn about new features.

Fabric Data Days Carousel

Fabric Data Days

Advance your Data & AI career with 50 days of live learning, contests, hands-on challenges, study groups & certifications and more!

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.

Top Solution Authors
Top Kudoed Authors