Forum Discussion
Hard coded days as working days column
- 2 years ago
Hi sraj - slight adjustment of your calculation as below:
WorkingDay 2 =
SWITCH(
TRUE(),
'Calendar'[Date] = DATE(2024, 6, 22) ||
'Calendar'[Date] = DATE(2024, 6, 29) ||
'Calendar'[Date] = DATE(2024, 7, 13) ||
'Calendar'[Date] = DATE(2024, 7, 20), "working day",ISBLANK('Calendar'[HolidayColumn]) && 'Calendar'[Day of week] <= 5, "working day",
ISBLANK('Calendar'[HolidayColumn]) && 'Calendar'[Day of week] >= 6, "weekend",
"Holiday"
)Hope it works
Did I answer your question? Mark my post as a solution! This will help others on the forum!
Appreciate your Kudos!!
Hi sraj - slight adjustment of your calculation as below:
WorkingDay 2 =
SWITCH(
TRUE(),
'Calendar'[Date] = DATE(2024, 6, 22) ||
'Calendar'[Date] = DATE(2024, 6, 29) ||
'Calendar'[Date] = DATE(2024, 7, 13) ||
'Calendar'[Date] = DATE(2024, 7, 20), "working day",
ISBLANK('Calendar'[HolidayColumn]) && 'Calendar'[Day of week] <= 5, "working day",
ISBLANK('Calendar'[HolidayColumn]) && 'Calendar'[Day of week] >= 6, "weekend",
"Holiday"
)
Hope it works
Did I answer your question? Mark my post as a solution! This will help others on the forum!
Appreciate your Kudos!!