prepo
Regular Visitor

Gantt chart error

Hello,

 

I am using Gantt chart by MAQ software, it was working well until I updated to the latest version of PowerBI (Version: 2.58.5103.501 64-bit (May 2018). Has anyone else encountered similar issues?maq.png

Thanks. 

1 ACCEPTED SOLUTION
MAQSupport
Solution Supplier
Solution Supplier

Hello, 

 

To display the bars in Gantt Chart using MAQ Software, please format the columns to be dragged in Start and End fields, as Date or Date/Time.

 

Thanks.

View solution in original post

5 REPLIES 5
MAQSupport
Solution Supplier
Solution Supplier

Hello, 

 

To display the bars in Gantt Chart using MAQ Software, please format the columns to be dragged in Start and End fields, as Date or Date/Time.

 

Thanks.

Thank you fpr your help, the error is resolved. 

v-shex-msft
Community Support
Community Support

HI @prepo,

 

Since you are not use official gantt custom visual, I also not know why they not works.(it may due to compatibility for visual code and new power bi features)

 

In my opinion, I'd like to suggest you contact to third party author for better support.

 

Regards,

XIaoxin Sheng

Community Support Team _ Xiaoxin
If this post helps, please consider accept as solution to help other members find it more quickly.

Hi Xlaoxin,

 

I tried the official Gantt chart visual as well and it switches all the project start dates to today’s date. I tried multiple formats of date, date and time, epoch start nothing worked. The start date of the effort highlighted in the screenshot is May 1, 2018. 

 

Data used

 

Test dataStart DateDurationActual

Change assignment & Lifecycle

2018/01/011802018-06-30

User Defined Metadata

2018/04/022732018-12-31

Visual Change Board

2018/05/011162018-08-25

Visual Reporting

2018/05/07852018-07-31

Templates

2017/11/011472018-03-28

Support change record 

2018/02/012402018-09-29
Dashboard creation2018/07/16-1622018-02-04

User defined logic and approval workflows

2018/05/071162018-08-31

Linkage to CI

2018/03/011212018-06-30

Updating configuration item 

2018/03/011832018-08-31

 

pbi issue.PNG

 

Thanks,

-P

Hi Xlaoxin,

 

I tried the official Gantt chart visual as well and it switches all the project start dates to today’s date. I tried multiple formats of date, date and time, epoch start nothing worked. The start date of the effort highlighted in the screenshot is May 1, 2018. 

 

Data used

 

Test dataStart DateDurationActual

Change assignment & Lifecycle

2018/01/011802018-06-30

User Defined Metadata

2018/04/022732018-12-31

Visual Change Board

2018/05/011162018-08-25

Visual Reporting

2018/05/07852018-07-31

Templates

2017/11/011472018-03-28

Support change record 

2018/02/012402018-09-29
Dashboard creation2018/07/16-1622018-02-04

User defined logic and approval workflows

2018/05/071162018-08-31

Linkage to CI

2018/03/011212018-06-30

Updating configuration item 

2018/03/011832018-08-31

 

pbi issue.PNG

 

Thanks,

-P

Helpful resources

Announcements
Microsoft Fabric Learn Together

Microsoft Fabric Learn Together

Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City

PBI_APRIL_CAROUSEL1

Power BI Monthly Update - April 2024

Check out the April 2024 Power BI update to learn about new features.

April Fabric Community Update

Fabric Community Update - April 2024

Find out what's new and trending in the Fabric Community.