Hi,
I am looking to visualise gantt chart where the actual start date is different from the plan date. Most of the custom visuals which i explored has the % of completion from the plan date, but does not provide details on the actual start date.
Is there any way to show Plan, Actuals and completion % for each task catagory in Gantt chart visual? Thanks for help !
@rajdivate , I used matrix once for project plan
Matrix as Project plan Visual: https://youtu.be/R25QoiyoSVs
If this does not help
Can you share sample data and sample output in table format? Or a sample pbix after removing sensitive data.
Thank You Amit Chandak sir for your quick response. I am basically looking to create similar visual as pasted below, where i should be able to filter - Plan, Actuals, % completion and overlap between Plan and Actuals (both).
Hi @rajdivate ,
Please review the links which have the same requirement as yours, hope they can help you resolve your problem.
Create A Gantt Chart In Power BI With A Matrix Visual
GANTT chart visuals in Power BI
Best Regards
Thank You !
Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City
Check out the April 2024 Power BI update to learn about new features.
User | Count |
---|---|
114 | |
105 | |
79 | |
68 | |
63 |
User | Count |
---|---|
148 | |
107 | |
106 | |
82 | |
70 |