I'm trying to change the start of week day within the Gantt chart header from Sunday to Monday.
Current:
Jul 31 (Sunday), Aug 07 (Sunday), Aug 14 (Sunday), Aug 21 (Sunday), etc...
Goal:
Aug 01 (Monday), Aug 08 ( Monday), Aug 15 (Monday), Aug 22 (Monday), etc...
My current understanding is that this has the same limitations as the relative date slicer, but I thought I would check just in case.
Solved! Go to Solution.
Hi @DLang ,
It is currently not possible to change the week start date of the Gantt chart. A workaround is to enable the "Days off" option to mark the end date of each week.
Or use the PowerGantt Chart visual, which uses Monday as the first day of the week.
Best Regards,
Winniz
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Is this still not possible in Gantt 2.2.3?
Hi @DLang ,
It is currently not possible to change the week start date of the Gantt chart. A workaround is to enable the "Days off" option to mark the end date of each week.
Or use the PowerGantt Chart visual, which uses Monday as the first day of the week.
Best Regards,
Winniz
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Check out the November 2025 Power BI update to learn about new features.
Advance your Data & AI career with 50 days of live learning, contests, hands-on challenges, study groups & certifications and more!