Hello!
When extracting data from Project Web, I can only see the distribution of hours by months accumulated in the month in which the task ends, but what I would need is to distribute the hours equally during the months it lasts.
For example here you see 3 tasks one of them has 312 hours of effort and in the table points them to the month of July 2024.
Any idea how to do it?
@Syndicate_Admin , refer if these can help
Measure way
Power BI Dax Measure- Allocate data between Range: https://youtu.be/O653vwLTUzM
https://community.powerbi.com/t5/Community-Blog/How-to-divide-distribute-values-between-start-date-o...
Matrix as Project plan Visual: https://youtu.be/R25QoiyoSVs
The Power BI Data Visualization World Championships is back! Get ahead of the game and start preparing now!
| User | Count |
|---|---|
| 38 | |
| 36 | |
| 33 | |
| 32 | |
| 29 |
| User | Count |
|---|---|
| 129 | |
| 88 | |
| 79 | |
| 68 | |
| 63 |