Display Shortest & Longest Project Duration

Hello - 

 

I'm working with a large time entry data set. I'm looking to show 2 cards, 1) with the shortest project duration and 2) with the longest project duration. 

 

What is the best way to show this? 

 

Thanks in advance,

Matt 

1 ACCEPTED SOLUTION
Anonymous
Not applicable

Hi

Create 2 new measures

 

Shortest_Duration = MIN(Proj_duration)

Longest_Duration= MAX(Proj_duration)

 

and place them on 2 cards.

 

Thanks

Raj

View solution in original post

1 REPLY 1
Anonymous
Not applicable

Hi

Create 2 new measures

 

Shortest_Duration = MIN(Proj_duration)

Longest_Duration= MAX(Proj_duration)

 

and place them on 2 cards.

 

Thanks

Raj

Helpful resources

Announcements
Power BI DataViz World Championships

Power BI Dataviz World Championships

The Power BI Data Visualization World Championships is back! Get ahead of the game and start preparing now!

December 2025 Power BI Update Carousel

Power BI Monthly Update - December 2025

Check out the December 2025 Power BI Holiday Recap!

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.