Define Days Off for Gantt Chart
Hello,
I found the option to highlith days off in Gantt Chart. Two questions:
- Is it possible to elapse the duration of the same amount of days off? i.e. I have two week-end "sunk" in my bar --> I want the bar to be 4 days longer.
- Is it possible to define a custom list of Days Off? By default only Saturday and Sunday are days off, is possible to enrich the list with bank holidays, summer shutdowns, etc ?
Thanks!
1 Reply
- v-henryk-mstfCommunity Support
Hi mballerio ,
For now, it seems that adding custom holidays to the days off option is not supported in the gantt chart.
If you do have a requirement, you can contact the developer of gantt chart to discuss this issue. Check out below community pages on Zendesk.