DAX help

 

 

Hi experts, 

I need to develop below matrix with few conditions

The sales amount will be depostited on the same day in case of bank working days.

Otherwise they will deposit on next banking day.

 

In below example, as you can see banks are closed on 25th and 26th december (Christmas and Sunday)

So they done the deposit on 27th december (25,26 and 26th sales).

Please help.

 

 

25-12-202126-12-202127-12-2021 28-12-2021 29-12-2021 
SaleSaleSaleDepositSaleDepositSaleDeposit
₹1,000.00₹500.00₹2,000.00₹3,500.00₹100.00₹100.00₹50.00₹50.00
        
  • Hi,

    I am not sure about which dates are your holidays, but I tried to create the sample like below.

    Please check the below picture and the attached pbix file.

    All measures are in the attached pbix file with numbering the steps from 01 to 05.

    In the sample, I assigned Saturday and Sunday as holidays, but you can assign your own holidays in your calendar table, and then apply the similar logic as what are in the attached pbix file.

    I hope this helps to apply and write similar measures for your data model.

     

3 Replies

  • Hi,

    I am not sure about which dates are your holidays, but I tried to create the sample like below.

    Please check the below picture and the attached pbix file.

    All measures are in the attached pbix file with numbering the steps from 01 to 05.

    In the sample, I assigned Saturday and Sunday as holidays, but you can assign your own holidays in your calendar table, and then apply the similar logic as what are in the attached pbix file.

    I hope this helps to apply and write similar measures for your data model.

     

    • Anonymous's avatar
      Anonymous
      Not applicable

      Thanks Jihwan_Kim , this is the exact solution I want. Thanks for your effort and time.

  • Anonymous's avatar
    Anonymous
    Not applicable

    Anonymous I'm hoping you have Date dimension table in the Model. if not please do.
    Step 1
    Create one Calculated column in the Date table

    IsWorkingDay = 
    VAR Result = 
    IF(
        dcalendar[WeekDay] IN {1,7} || dcalendar[Holiday],
        0,
        1
        
    )
    RETURN
    Result

    Step 2:- Create "ThisorNextWorkingDay" calculated column

    ThisorNextWorkingDay = 
    VAR NextWorkingDay = 
    MINX(
        FILTER(
            dcalendar,
            dcalendar[Date] > EARLIER( dcalendar[Date])
            && dcalendar[IsWorkingDay] = 1
        ),
        dcalendar[Date]
    )
    VAR Result = 
    IF( 
        dcalendar[IsWorkingDay] = 0 ,NextWorkingDay , dcalendar[Date] 
    )
    RETURN
    Result

    Output:- 

    Please mark the question solved when done and consider giving kudos if posts are helpful.