Hi experts, 

I need to develop below matrix with few conditions

The sales amount will be depostited on the same day in case of bank working days.

Otherwise they will deposit on next banking day.

 

In below example, as you can see banks are closed on 25th and 26th december (Christmas and Sunday)

So they done the deposit on 27th december (25,26 and 26th sales).

Please help.

 

 

25-12-202126-12-202127-12-2021 28-12-2021 29-12-2021 
SaleSaleSaleDepositSaleDepositSaleDeposit
₹1,000.00₹500.00₹2,000.00₹3,500.00₹100.00₹100.00₹50.00₹50.00
        
1 ACCEPTED SOLUTION
Jihwan_Kim
Super User
Super User

Hi,

I am not sure about which dates are your holidays, but I tried to create the sample like below.

Please check the below picture and the attached pbix file.

All measures are in the attached pbix file with numbering the steps from 01 to 05.

In the sample, I assigned Saturday and Sunday as holidays, but you can assign your own holidays in your calendar table, and then apply the similar logic as what are in the attached pbix file.

I hope this helps to apply and write similar measures for your data model.

Picture2.png 


If this post helps, then please consider accepting it as the solution to help other members find it faster, and give a big thumbs up.


Click here to visit my LinkedIn page

Click here to schedule a short Teams meeting to discuss your question.

View solution in original post

3 REPLIES 3
Jihwan_Kim
Super User
Super User

Hi,

I am not sure about which dates are your holidays, but I tried to create the sample like below.

Please check the below picture and the attached pbix file.

All measures are in the attached pbix file with numbering the steps from 01 to 05.

In the sample, I assigned Saturday and Sunday as holidays, but you can assign your own holidays in your calendar table, and then apply the similar logic as what are in the attached pbix file.

I hope this helps to apply and write similar measures for your data model.

Picture2.png 


If this post helps, then please consider accepting it as the solution to help other members find it faster, and give a big thumbs up.


Click here to visit my LinkedIn page

Click here to schedule a short Teams meeting to discuss your question.
Anonymous
Not applicable

Thanks @Jihwan_Kim , this is the exact solution I want. Thanks for your effort and time.

Anonymous
Not applicable

@Anonymous I'm hoping you have Date dimension table in the Model. if not please do.
Step 1
Create one Calculated column in the Date table

IsWorkingDay = 
VAR Result = 
IF(
    dcalendar[WeekDay] IN {1,7} || dcalendar[Holiday],
    0,
    1
    
)
RETURN
Result

Step 2:- Create "ThisorNextWorkingDay" calculated column

ThisorNextWorkingDay = 
VAR NextWorkingDay = 
MINX(
    FILTER(
        dcalendar,
        dcalendar[Date] > EARLIER( dcalendar[Date])
        && dcalendar[IsWorkingDay] = 1
    ),
    dcalendar[Date]
)
VAR Result = 
IF( 
    dcalendar[IsWorkingDay] = 0 ,NextWorkingDay , dcalendar[Date] 
)
RETURN
Result

Output:- 

kumarthombre20_0-1648452148186.png

Please mark the question solved when done and consider giving kudos if posts are helpful.

Helpful resources

Announcements
FabCon Global Hackathon Carousel

FabCon Global Hackathon

Join the Fabric FabCon Global Hackathon—running virtually through Nov 3. Open to all skill levels. $10,000 in prizes!

September Power BI Update Carousel

Power BI Monthly Update - September 2025

Check out the September 2025 Power BI update to learn about new features.

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.

Top Solution Authors
Top Kudoed Authors