Cummulative with measure not working

I'm trying to create a cummulative calcule but it's not working.

I've created 1 measure with Earned Value which is Earned Value = ([Planned Value BAC] * [Total of % Complete]) / 100

and then I created the

EV cummulative = CALCULATE([Earned Value], FILTER(ALLSELECTED(Budget),Budget[account_period] <= MAX(Budget[account_period])))

the result is diplayed below and the total is right, but it doesn't follow the sum. I've created also BAC cummulative and Actual cost cummulative and both works.

report.png

 

1 ACCEPTED SOLUTION
ftorres
Helper I
Helper I

I have to create a column Earned Value instead of a measure.

then the code below worked.

EV cummulative = CALCULATE([Earned Value], FILTER(ALLSELECTED(Budget),Budget[account_period] <= MAX(Budget[account_period])))

View solution in original post

4 REPLIES 4
ftorres
Helper I
Helper I

I have to create a column Earned Value instead of a measure.

then the code below worked.

EV cummulative = CALCULATE([Earned Value], FILTER(ALLSELECTED(Budget),Budget[account_period] <= MAX(Budget[account_period])))

Greg_Deckler
Super User
Super User

Tough to understand what is going on given the information provided. I take it that [Planned Value BAC] and [Total % Complete] are also measures? What are their formulas? What is the value of [Total % Complete] in the rows show below? What are your formulas for the cummulative totals that work?

 

Please see this post regarding How to Get Your Question Answered Quickly: https://community.powerbi.com/t5/Community-Blog/How-to-Get-Your-Question-Answered-Quickly/ba-p/38490


Follow on LinkedIn
@ me in replies or I'll lose your thread!!!
Instead of a Kudo, please vote for this idea
Become an expert!: Enterprise DNA
External Tools: MSHGQM
YouTube Channel!: Microsoft Hates Greg
Latest book!:
The Definitive Guide to Power Query (M)

DAX is easy, CALCULATE makes DAX hard...

Hi Greg,

Both are measures with SUM function.

Planned Value BAC = IF(SUM(Budget[budget_rev])<>0, SUM(Budget[budget_rev]), BLANK())

Total of % Complete = SUM(Budget[% Complete])

 

This measure below works

BAC cummulative = CALCULATE([Planned Value BAC],FILTER(ALLSELECTED(Budget),Budget[account_period] <= MAX(Budget[account_period])))

Hi @ftorres,

 

You formula seems well, can you please share a pbix file with some sample data for test?

 

In addition, you can also try to use following measure to calculate cumulative based on other measure:

Commulative =
VAR currPeriod =
    MAX ( Budget[account_period] )
VAR summary =
    ADDCOLUMNS ( ALLSELECTED ( Budget ), "EV", [Earned Value] )
RETURN
    SUMX ( FILTER ( summarize, Budget[account_period] <= currPeriod ), [EV] )

 

Regards,
Xiaoxin Sheng

Community Support Team _ Xiaoxin
If this post helps, please consider accept as solution to help other members find it more quickly.

Helpful resources

Announcements
Europe Fabric Conference

Europe’s largest Microsoft Fabric Community Conference

Join the community in Stockholm for expert Microsoft Fabric learning including a very exciting keynote from Arun Ulag, Corporate Vice President, Azure Data.

Power BI Carousel June 2024

Power BI Monthly Update - June 2024

Check out the June 2024 Power BI update to learn about new features.

RTI Forums Carousel3

New forum boards available in Real-Time Intelligence.

Ask questions in Eventhouse and KQL, Eventstream, and Reflex.