Convert Week number into date

Hi All,

How can I convert week no into date ?

So that I can use that in continuous X-Axis of my visual.

 

Thanks,

Arul





Did I answer your question? Mark my post as a solution!

Proud to be a Super User!


LinkedIn


1 ACCEPTED SOLUTION
amitchandak
Super User
Super User

@Arul , Assume you have Year and week no with you

 

New column =

var _st = date([Year],1,1)

var _st_week = _st  - weekday(_st ,2) +1 //monday week

return

_st_week + (7 *[week no])

Share with Power BI Enthusiasts: Full Power BI Video (20 Hours) YouTube
Microsoft Fabric Series 60+ Videos YouTube
Microsoft Fabric Hindi End to End YouTube

View solution in original post

2 REPLIES 2
amitchandak
Super User
Super User

@Arul , Assume you have Year and week no with you

 

New column =

var _st = date([Year],1,1)

var _st_week = _st  - weekday(_st ,2) +1 //monday week

return

_st_week + (7 *[week no])

Share with Power BI Enthusiasts: Full Power BI Video (20 Hours) YouTube
Microsoft Fabric Series 60+ Videos YouTube
Microsoft Fabric Hindi End to End YouTube

@amitchandak ,

It helps. Thank you





Did I answer your question? Mark my post as a solution!

Proud to be a Super User!


LinkedIn


Helpful resources

Announcements
Power BI DataViz World Championships

Power BI Dataviz World Championships

The Power BI Data Visualization World Championships is back! Get ahead of the game and start preparing now!

December 2025 Power BI Update Carousel

Power BI Monthly Update - December 2025

Check out the December 2025 Power BI Holiday Recap!

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.