Hi all,

 

I have a data set similar to the one below

 

Start DateDuration (Days)
01/01/20216
02/01/20217
01/02/20214

 

I want to create a calculated column titled 'End Date'. This end date needs to exclude weekends.

 

For example, if a task was to start on 24/05/2021 (Monday) and had a duration of 6 days. I would need the end date to be 31/05/2021 (Monday). 

 

Any help would be much appreciated.

 

Thanks,

 

Elliot

1 ACCEPTED SOLUTION
mahoneypat
Microsoft Employee
Microsoft Employee

Please see this video.  It shows how to do it in either DAX or M.

(11) Power BI - Tales from the Front #03 - Due Date From Working Days - YouTube

 

Pat





Did I answer your question? Mark my post as a solution! Kudos are also appreciated!

To learn more about Power BI, follow me on Twitter or subscribe on YouTube.


@mahoneypa HoosierBI on YouTube


View solution in original post

1 REPLY 1
mahoneypat
Microsoft Employee
Microsoft Employee

Please see this video.  It shows how to do it in either DAX or M.

(11) Power BI - Tales from the Front #03 - Due Date From Working Days - YouTube

 

Pat





Did I answer your question? Mark my post as a solution! Kudos are also appreciated!

To learn more about Power BI, follow me on Twitter or subscribe on YouTube.


@mahoneypa HoosierBI on YouTube


Helpful resources

Announcements
July 2025 community update carousel

Fabric Community Update - July 2025

Find out what's new and trending in the Fabric community.

July PBI25 Carousel

Power BI Monthly Update - July 2025

Check out the July 2025 Power BI update to learn about new features.

Top Solution Authors