Calculate Time Between
Hi all, How can create the column 'Break' below? It calculates the time between the end of the shift and start of the next one. They can be on different dates but have to be the next day work...
- 5 years ago
Hi HenryJS ,
Start_time = VAR __start = MAX(Sheet7[Start]) RETURN DATE(2020, 1, 2) + __startEnd_time = VAR __end = CALCULATE( MAX([End]), FILTER( ALL(Sheet7), Sheet7[Timesheet ID] = MAX(Sheet7[Timesheet ID]) && Sheet7[Date] < MAX(Sheet7[Date]) ) ) RETURN IF( __end <> BLANK(), DATE(2020,1,1) + __end, BLANK() )Measure 2 = IF( [End_time] <> BLANK(), [Start_time] - [End_time], TIME(0,0,0) )Best regards,
Lionel ChenIf this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
amitchandak
5 years agoSuper User
HenryJS , Try new columns like
create new columns
start time = [Date] + [start]
End time = [Date] + [end]
Break = maxx(flter(Table, [Timesheet ID] =earlier([Timesheet ID]) && [Date]<earlier([date])),[End time]) -[start time]
- HenryJS5 years agoPost Prodigy
amitchandak thanks that works!
However on the first instance it calculates a break time even though there's no shift before?