Hi Taffalaffa ,
Try the following code for the columns (I added on the Base Data Table):
Planned Dur (D) = SWITCH ( TRUE (), 'Base Data'[Holiday?] = "Holidays", COUNTROWS ( FILTER ( ALL ( 'Date Table' ), 'Date Table'[Date] <= 'Base Data'[Finish] && 'Date Table'[Date] >= 'Base Data'[Start] && VAR Calendar_type = SWITCH ( 'Base Data'[Calendar Type], "5 Day", 'Date Table'[5 Day (H)], "6 Day", 'Date Table'[6 Day (H)], "7 Day", 'Date Table'[7 Day (H)] ) RETURN Calendar_type = "Workday" ) ), 'Base Data'[Holiday?] = "No Holidays", COUNTROWS ( FILTER ( ALL ( 'Date Table' ), 'Date Table'[Date] <= 'Base Data'[Finish] && 'Date Table'[Date] >= 'Base Data'[Start] && VAR Calendar_type = SWITCH ( 'Base Data'[Calendar Type], "5 Day", 'Date Table'[5 Day (NH)], "6 Day", 'Date Table'[6 Day (NH)], "7 Day", 'Date Table'[7 Day (NH)] ) RETURN Calendar_type = "Workday" ) ) ) Act Dur (D) = SWITCH ( TRUE (), 'Base Data'[Activity Status] = "Not Started", 0, 'Base Data'[Holiday?] = "Holidays", COUNTROWS ( FILTER ( ALL ( 'Date Table' ), VAR Status_value = SWITCH ( 'Base Data'[Activity Status], "Completed", 'Base Data'[Actual Finish], "In Progress", 'Base Data'[Data Date] ) RETURN 'Date Table'[Date] <= Status_value && 'Date Table'[Date] >= 'Base Data'[Actual Start] && VAR Calendar_type = SWITCH ( 'Base Data'[Calendar Type], "5 Day", 'Date Table'[5 Day (H)], "6 Day", 'Date Table'[6 Day (H)], "7 Day", 'Date Table'[7 Day (H)] ) RETURN Calendar_type = "Workday" ) ), 'Base Data'[Holiday?] = "No Holidays", COUNTROWS ( FILTER ( ALL ( 'Date Table' ), VAR Status_value = SWITCH ( 'Base Data'[Activity Status], "Completed", 'Base Data'[Actual Finish], "In Progress", 'Base Data'[Data Date] ) RETURN 'Date Table'[Date] <= Status_value && 'Date Table'[Date] >= 'Base Data'[Actual Start] && VAR Calendar_type = SWITCH ( 'Base Data'[Calendar Type], "5 Day", 'Date Table'[5 Day (NH)], "6 Day", 'Date Table'[6 Day (NH)], "7 Day", 'Date Table'[7 Day (NH)] ) RETURN Calendar_type = "Workday" ) ) ) At Complete Duration = SWITCH ( 'Base Data'[Activity Status], "Completed", 'Base Data'[Act Dur (D)], "In Progress", 'Base Data'[Remain Dur (D)] + 'Base Data'[Act Dur (D)], "Not Started", 'Base Data'[Remain Dur (D)] )Has you can see below result is matching the excel file:
PBIX file attach.
- 4 years ago
Oh my goodness this is perfect! I truly cannot thank you enough for your help! Thank you so very much!
Hi Taffalaffa ,
Sorry for the follow up quesiton on the example I gave you this is a 5 day calendar the saturdays are non working day should I double count the holidays? On the Excel it's double counting on the specific example I send out.
Hi Felix,
To simplify (and not make me get out a calendar to count all the days in the example you put!) If we have an activity that started 12/20 and ended 1/3 and was on a:
1. 6 Day (H) calendar then that should show as 9 days duration
2. 5 Day (H) calendar then it should show as 9 days duration
3. 6 Day (NH) then it should show as 13 days duration
4. 5 Day (NH) then it should show as 11 Days duration
5. 7 Day (H) then it should show as 11 Days Duration
6. 7 Day (NH) then it should show as 15 Days Duration
on the Calendars that celebrate Holidays, the federal observed holiday for Christmas this year is 12/24 and New Years is 12/31 so even though it is on 5/6/7 day holiday calendar neither Friday or Saturday would be work days in this scenario (but Sunday still would be on the 7 Day)
I see now that my dates table in excel is wrong because it did not account for the observed holidays dates when the holiday fell on a Saturday. I will update and resend!
Does that answer your question?
- MFelix4 years agoSuper User
Thank you . will check and get back to you.