Adding measures and calculated columns

Hello,

 

I am being asked to create a calculated RYG for each project and as part of that, I've created table that provides a KPI for scope (measuring how far over or under).  From this KPI, we generate a score using a calculated column

c_Scope Score =
SWITCH(
TRUE(),
'BurndownScope'[Ratio]<=1.3,1,
'BurndownScope'[Ratio]<=1.5,2,
'BurndownScope'[Ratio]>1.5,3
)
 
I then created a calculated column that adds the 4 components of the RYG together to generate an overall score.  The problem I'm running into is with the scope score.  Because it is a column, I can't add it w/o some sort of aggregator, which then gives me the wrong number for the overall score.  How do I pass the scope score for each project to the calculation for the Overall Project score?
 
Dax for overall project score metric
c_Overall Project Score =
'Risks'[m_Project Risk Score]
+
'Issues'[m_Project Issue Score]
+
'Projects'[M_Sched Perf]
+
'burndownscope'[c_Scope Score]
3 REPLIES 3
v-juanli-msft
Community Support
Community Support

Hi @Clint 

What is the relationship amonth the four tables?

'Risks',Issues',Projects',burndownscope'
 
When adding four columns in one table visual, how does it look like?
'Risks'[m_Project Risk Score]
'Issues'[m_Project Issue Score]
'Projects'[M_Sched Perf]
'burndownscope'[c_Scope Score]
 

Could you give some data samples so that i can reproduce your problem?

 

Best Regards
Maggie

 

 

Hi Maggie,

 

Risk and Issues are related to the Projects Table via the ProjectID field.  The scope score is generated from a table that tracks the current scope and baseilne scope and is related to a table that tracks weekly burndown (and provides scope values) via the clarity ID in a many to one.  The Burdowns table is related to the Project Table via the Clarity ID (see embedded image).  This is a many to many relationship unfortunately.  

I am using the "average" function to generate the overall project score in the Project Score table.

Project Score

 

project score table.PNGRelationships

relationships.PNG

Clint
Helper V
Helper V

The table that has the burn down scope looks like this:

burndown scope table.PNG

There's only one value for each project so I'm not clear as to why I need an aggregator?


@Clint wrote:

Hello,

 

I am being asked to create a calculated RYG for each project and as part of that, I've created table that provides a KPI for scope (measuring how far over or under).  From this KPI, we generate a score using a calculated column

c_Scope Score =
SWITCH(
TRUE(),
'BurndownScope'[Ratio]<=1.3,1,
'BurndownScope'[Ratio]<=1.5,2,
'BurndownScope'[Ratio]>1.5,3
)
 
I then created a calculated column that adds the 4 components of the RYG together to generate an overall score.  The problem I'm running into is with the scope score.  Because it is a column, I can't add it w/o some sort of aggregator, which then gives me the wrong number for the overall score.  How do I pass the scope score for each project to the calculation for the Overall Project score?
 
Dax for overall project score metric
c_Overall Project Score =
'Risks'[m_Project Risk Score]
+
'Issues'[m_Project Issue Score]
+
'Projects'[M_Sched Perf]
+
'burndownscope'[c_Scope Score]

 

Helpful resources

Announcements
Power BI DataViz World Championships

Power BI Dataviz World Championships

The Power BI Data Visualization World Championships is back! Get ahead of the game and start preparing now!

December 2025 Power BI Update Carousel

Power BI Monthly Update - December 2025

Check out the December 2025 Power BI Holiday Recap!

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.