Add number of working days to a date - power query included

Hi all,

 

I have a tiny problem that I am most likely overthinking. 

I have a requirement to add a number to a date in working days. So far I got it. I had to merge some queries and I have used Date.AddDays query to get my 'Result'.

Below table is a sample result from my data. It looks great and does exactly what is asked of it.

I now need to be able to omit Saturdays and Sundays if my result happens to be a saturday or sunday: 

 

Original DateDays to add  Result Working day? Ideal Result
29/06/2020504/07/2020No, it's a Saturday

06/07/2020

(Monday)

 

I have created a date dimension table that simply works out week numbers and then determines if a date is a working one or not ( 1,0)

 2020-07-20_12-12-39.jpg

 

Has anyone completed anything like this before? I nudge in the right direction would be much appreciated! 

Thanks! 

1 ACCEPTED SOLUTION
Fowmy
Super User
Super User

@kasiaw29 

This will be your new column to show the expected Result date:

=let D = Date.AddDays([Original Date],[Days To Add]) in 

if Date.DayOfWeek(D,Day.Saturday)=0 then Date.AddDays(D,2)

else if

Date.DayOfWeek(D,Day.Saturday)=1 then Date.AddDays(D,1)

else

D

Fowmy_0-1595247127985.png

 

________________________

Did I answer your question? Mark this post as a solution, this will help others!.

I accept KUDOS ☺

YouTube | LinkedIn

Did I answer your question? Mark my post as a solution! and hit thumbs up


Subscribe and learn Power BI from these videos

Website LinkedIn PBI User Group

View solution in original post

5 REPLIES 5
Fowmy
Super User
Super User

@kasiaw29 

This will be your new column to show the expected Result date:

=let D = Date.AddDays([Original Date],[Days To Add]) in 

if Date.DayOfWeek(D,Day.Saturday)=0 then Date.AddDays(D,2)

else if

Date.DayOfWeek(D,Day.Saturday)=1 then Date.AddDays(D,1)

else

D

Fowmy_0-1595247127985.png

 

________________________

Did I answer your question? Mark this post as a solution, this will help others!.

I accept KUDOS ☺

YouTube | LinkedIn

Did I answer your question? Mark my post as a solution! and hit thumbs up


Subscribe and learn Power BI from these videos

Website LinkedIn PBI User Group

Hey @Fowmy ! 

 

I ended up doing pretty much what you have suggested and it works a treat! 

 

Thanks a lot for input!

@kasiaw29 

Glad it worked for you!

________________________

Did I answer your question? Mark this post as a solution, this will help others!.

I accept KUDOS 🙂

YouTube | LinkedIn

Did I answer your question? Mark my post as a solution! and hit thumbs up


Subscribe and learn Power BI from these videos

Website LinkedIn PBI User Group

amitchandak
Super User
Super User

@kasiaw29 , not completely clear.  In case you want to add or subtract working days

refer : https://community.powerbi.com/t5/Community-Blog/Travelling-Across-Workdays-Decoding-Date-and-Calenda...

Share with Power BI Enthusiasts: Full Power BI Video (20 Hours) YouTube
Microsoft Fabric Series 60+ Videos YouTube
Microsoft Fabric Hindi End to End YouTube

Thanks @amitchandak will look through this solution and update shrotly. 

Helpful resources

Announcements
FabCon Global Hackathon Carousel

FabCon Global Hackathon

Join the Fabric FabCon Global Hackathon—running virtually through Nov 3. Open to all skill levels. $10,000 in prizes!

September Power BI Update Carousel

Power BI Monthly Update - September 2025

Check out the September 2025 Power BI update to learn about new features.

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.

Top Solution Authors
Top Kudoed Authors