hi friends,
I want to get planned value for future weeks.
I have planned value table with all data(week and corresponding PV value for each project also for future week)
and also I have project table with data of each project and earned value of each week,(which has data upto current week)
also I have calender table . both table is connected to week num of calender. but when I add all data to visual it only shows upto current week and not future weeks of pv.
how to solve this. Any help would be appreciated:)
in project table the date is upto current week and from that date week and year is calculated and connected with calender week and year
is this wrong and is that the reason why its getting restricted to current week or my mapping is wrong?
Hi,
Share some data and show the expected result.
how to get for future week like202338 or 202348
The Power BI Data Visualization World Championships is back! Get ahead of the game and start preparing now!
| User | Count |
|---|---|
| 14 | |
| 7 | |
| 4 | |
| 4 | |
| 3 |
| User | Count |
|---|---|
| 23 | |
| 10 | |
| 10 | |
| 6 | |
| 5 |