Hi Guys,
I hope you are all well.
See link: PBIX FILE
To summarize what I'm looking to do:
I'm analysing how legal files pass through a legal process (190 steps). I have the actual days each file takes to go through the legal steps, and the expected days it should take. I want to create a forecast of total days required from the current legal step to completion.
The remaining forecast for me is a stepping stone to get to an "expected completion date" for the file. You will see that the FactExpectedFile has no date since it is just a target (Expected days per legal step). I would further like to add the remaining value to the Latest Activity Date, but will tackle this afterwards :).
I followed the SQLBI.com's excellent post "Showing forecast and actuals in the same chart with Power BI" and I've built a similar code
Remaining Expected Steps =
VAR LastLegalStep =
CALCULATE(
MAX( FactFiles[LegalSubStepIndex] ),
FILTER( DimCurrentStep, DimCurrentStep[Legal Step] = "Current"))
// this get me the current legal step the file
VAR RemainingLegalSteps =
CALCULATE(
[Expected Days],
KEEPFILTERS( FactFiles[LegalSubStepIndex] >= LastLegalStep )
)
RETURN
RemainingLegalSteps
But its not working. I just get the expected days for all the steps.
the first part of te code is correct and I get the right value, but not the second part...?
Can anyone help?
I hope this is enough information to go on?
Thank you in advance!
The Power BI Data Visualization World Championships is back! Get ahead of the game and start preparing now!
Check out the November 2025 Power BI update to learn about new features.
| User | Count |
|---|---|
| 20 | |
| 10 | |
| 9 | |
| 4 | |
| 4 |
| User | Count |
|---|---|
| 32 | |
| 31 | |
| 18 | |
| 12 | |
| 11 |