How to Get the Total Benefit for the left over months?

Calculation :

Assume a project has a “Total Benefit” per year of £120. The following table shows how to chart the annual benefit depending on the project completion date. Please help me on the DAX formula in achieving the annual benefits for the years 2022 to 2026.

 

Project completion date

2022

2023

2024

2025

2026

Notes

30Jun22

£60

£120

£120

£120

£120

Benefits start in July 22 = Six months of benefit in 2022 = (£120/12) x 6 = £60

31Oct22

£20

£120

£120

£120

£120

Benefits start in November 22 = 2 months of benefit in 2022 = (£120/12) x2  = £20

31Dec22

£0

£120

£120

£120

£120

Benefits start in January 23 = 12 months of benefit in 2023 = £120

31Mar23

£0

£90

£120

£120

£120

Benefits start in March 23 = 9 months of benefit in 2023 = (£120/12) x9  = £90

31Oct23

£0

£20

£120

£120

£120

Benefits start in November 23 = 2 months of benefit in 2023 = (£120/12) x2  = £20

 

Please help me in providing the DAX for the following requirement. It would be really helpful.

Thanks in advance !!

1 REPLY 1
littlemojopuppy
Community Champion
Community Champion

@MadhumithaV_26 can you share some raw data?  Not what you expect the finished product to be

Helpful resources

Announcements
September Power BI Update Carousel

Power BI Monthly Update - September 2025

Check out the September 2025 Power BI update to learn about new features.

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.