FTE caculation using assigned work

Hi I'm new to DAX formulas

 

I'm using the Power BI content pack for PWA data and am trying to calculate monthly FTE using hours currently assigned to resources "assignment work".  Under the TimeSet table I have written two measures which calculate working days per month and working hours based on an 8 hour working day. 

 

Working Hours = TimeSet[Working Days]*8
Working Days = CALCULATE(COUNTA(TimeSet[TimeByDay]),TimeSet[Is Working Day]="yes")
 
Now I want to divide Assignment Work by Working Hours to calculate the FTE but the Assignment Work is in AssignmentTimePhaseDataSet and I don't know what DAX formula I need.
 
Can you please help!, cheers, Vanessa
 
VFlood1971_0-1624856244540.png

 

2 REPLIES 2
Tanushree_Kapse
Impactful Individual
Impactful Individual

Hi @Anonymous ,
For this, you need to create relationship between these two table. Then only you would get the correct data in the visual.

Anonymous
Not applicable

Hi there

They are already linked - does it need to be a particular kind of relationship?

VFlood1971_0-1624945463285.png

cheers

Vanessa

Helpful resources

Announcements
Power BI DataViz World Championships

Power BI Dataviz World Championships

The Power BI Data Visualization World Championships is back! Get ahead of the game and start preparing now!

December 2025 Power BI Update Carousel

Power BI Monthly Update - December 2025

Check out the December 2025 Power BI Holiday Recap!

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.