DAX Statement: Conditional

This is my first post for help as I am relativley new to PowerBI! Hoping this maybe a quick fix? 
 
Test =
IF(
'00_Master Schedule'[Design release date for Works Information] <= '00_Master Schedule'[Asite Export Master.Date (WET)] ,
"On-Time" ,
IF(
'00_Master Schedule'[Design release date for Works Information] > '00_Master Schedule'[Asite Export Master.Date (WET)] ,
"Late" ,
IF(
'00_Master Schedule'[Design release date for Works Information] <= DATE(TODAY(), && '00_Master Schedule'[Stage 1: Design Upload] = "Not Released" , "Overdue"
))))
1 ACCEPTED SOLUTION
amitchandak
Super User
Super User

@Anonymous , Better to use Switch

Test =
SWitch( True(), 
'00_Master Schedule'[Design release date for Works Information] <= '00_Master Schedule'[Asite Export Master.Date (WET)] ,
"On-Time" ,
'00_Master Schedule'[Design release date for Works Information] > '00_Master Schedule'[Asite Export Master.Date (WET)] ,
"Late" ,
'00_Master Schedule'[Design release date for Works Information] <= TODAY() && '00_Master Schedule'[Stage 1: Design Upload] = "Not Released" 
, "Overdue"
)
Full Power BI Video 20 Hours YouTube
Microsoft Fabric Series 60+ Videos YouTube
Microsoft Fabric Hindi End to End YouTube

View solution in original post

2 REPLIES 2
amitchandak
Super User
Super User

@Anonymous , Better to use Switch

Test =
SWitch( True(), 
'00_Master Schedule'[Design release date for Works Information] <= '00_Master Schedule'[Asite Export Master.Date (WET)] ,
"On-Time" ,
'00_Master Schedule'[Design release date for Works Information] > '00_Master Schedule'[Asite Export Master.Date (WET)] ,
"Late" ,
'00_Master Schedule'[Design release date for Works Information] <= TODAY() && '00_Master Schedule'[Stage 1: Design Upload] = "Not Released" 
, "Overdue"
)
Full Power BI Video 20 Hours YouTube
Microsoft Fabric Series 60+ Videos YouTube
Microsoft Fabric Hindi End to End YouTube
nandic
Super User
Super User

@Anonymous ,

Try this:
Test =
IF (
    '00_Master Schedule'[Design release date for Works Information] <= '00_Master Schedule'[Asite Export Master.Date (WET)],
    "On-Time",
    IF (
        '00_Master Schedule'[Design release date for Works Information] > '00_Master Schedule'[Asite Export Master.Date (WET)],
        "Late",
        IF (
            AND (
                '00_Master Schedule'[Design release date for Works Information] <= TODAY (),
                '00_Master Schedule'[Stage 1: Design Upload] = "Not Released"
            ),
            "Overdue"
        )
    )
)

You used function DATE(TODAY()), but date function expects these parameters: year, month, day so it results in error.

Helpful resources

Announcements
Join our Fabric User Panel

Join our Fabric User Panel

This is your chance to engage directly with the engineering team behind Fabric and Power BI. Share your experiences and shape the future.

June 2025 Power BI Update Carousel

Power BI Monthly Update - June 2025

Check out the June 2025 Power BI update to learn about new features.

June 2025 community update carousel

Fabric Community Update - June 2025

Find out what's new and trending in the Fabric community.

Top Solution Authors