DAX Statement: Conditional

This is my first post for help as I am relativley new to PowerBI! Hoping this maybe a quick fix? 
 
Test =
IF(
'00_Master Schedule'[Design release date for Works Information] <= '00_Master Schedule'[Asite Export Master.Date (WET)] ,
"On-Time" ,
IF(
'00_Master Schedule'[Design release date for Works Information] > '00_Master Schedule'[Asite Export Master.Date (WET)] ,
"Late" ,
IF(
'00_Master Schedule'[Design release date for Works Information] <= DATE(TODAY(), && '00_Master Schedule'[Stage 1: Design Upload] = "Not Released" , "Overdue"
))))
1 ACCEPTED SOLUTION
amitchandak
Super User
Super User

@Anonymous , Better to use Switch

Test =
SWitch( True(), 
'00_Master Schedule'[Design release date for Works Information] <= '00_Master Schedule'[Asite Export Master.Date (WET)] ,
"On-Time" ,
'00_Master Schedule'[Design release date for Works Information] > '00_Master Schedule'[Asite Export Master.Date (WET)] ,
"Late" ,
'00_Master Schedule'[Design release date for Works Information] <= TODAY() && '00_Master Schedule'[Stage 1: Design Upload] = "Not Released" 
, "Overdue"
)
Share with Power BI Enthusiasts: Full Power BI Video (20 Hours) YouTube
Microsoft Fabric Series 60+ Videos YouTube
Microsoft Fabric Hindi End to End YouTube

View solution in original post

2 REPLIES 2
amitchandak
Super User
Super User

@Anonymous , Better to use Switch

Test =
SWitch( True(), 
'00_Master Schedule'[Design release date for Works Information] <= '00_Master Schedule'[Asite Export Master.Date (WET)] ,
"On-Time" ,
'00_Master Schedule'[Design release date for Works Information] > '00_Master Schedule'[Asite Export Master.Date (WET)] ,
"Late" ,
'00_Master Schedule'[Design release date for Works Information] <= TODAY() && '00_Master Schedule'[Stage 1: Design Upload] = "Not Released" 
, "Overdue"
)
Share with Power BI Enthusiasts: Full Power BI Video (20 Hours) YouTube
Microsoft Fabric Series 60+ Videos YouTube
Microsoft Fabric Hindi End to End YouTube
nandic
Super User
Super User

@Anonymous ,

Try this:
Test =
IF (
    '00_Master Schedule'[Design release date for Works Information] <= '00_Master Schedule'[Asite Export Master.Date (WET)],
    "On-Time",
    IF (
        '00_Master Schedule'[Design release date for Works Information] > '00_Master Schedule'[Asite Export Master.Date (WET)],
        "Late",
        IF (
            AND (
                '00_Master Schedule'[Design release date for Works Information] <= TODAY (),
                '00_Master Schedule'[Stage 1: Design Upload] = "Not Released"
            ),
            "Overdue"
        )
    )
)

You used function DATE(TODAY()), but date function expects these parameters: year, month, day so it results in error.

Helpful resources

Announcements
FabCon Global Hackathon Carousel

FabCon Global Hackathon

Join the Fabric FabCon Global Hackathon—running virtually through Nov 3. Open to all skill levels. $10,000 in prizes!

September Power BI Update Carousel

Power BI Monthly Update - September 2025

Check out the September 2025 Power BI update to learn about new features.

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.