Supplies are limited. Contact info@espc.tech right away to save your spot before the conference sells out.
Get your discountScore big with last-minute savings on the final tickets to FabCon Vienna. Secure your discount
I have searched the forums with *almost* success but the DAX I've found isn't helping. I have a project table in which I'm trying to calculate the length of the overal project (Project Name). In this example, the total project duration would be the datediff of 6/11/2018 - 5/4/2023, or 1788 days. Thanks in advance for any assistance!!
LineID | Project Name | Category | Subcategory | Actual Start | Actual/Forecasted Finish | Current Duration |
500 | Project A | Design | ROW | 6/11/2018 | 11/9/2018 | 151 |
501 | Project A | Design | ROW | 10/12/2018 | 10/16/2019 | 369 |
502 | Project A | Design | Planning | 1/31/2019 | 12/4/2019 | 307 |
503 | Project A | Design | Environmental | 11/19/2018 | 2/28/2020 | 466 |
504 | Project A | Design | Environmental | 1/23/2019 | 8/31/2020 | 586 |
505 | Project A | Design | Environmental | 1/18/2019 | 5/28/2020 | 496 |
506 | Project A | Design | Environmental | 4/24/2019 | 1/8/2020 | 259 |
507 | Project A | Design | Environmental | 2/21/2020 | 5/20/2020 | 89 |
508 | Project A | Design | ROW | 7/15/2019 | 12/2/2020 | 506 |
509 | Project A | Design | Environmental | 11/21/2019 | 11/16/2020 | 361 |
510 | Project A | Design | Environmental | 12/4/2019 | 11/17/2020 | 349 |
512 | Project A | Design | Final Design | 12/31/2019 | 5/18/2020 | 139 |
513 | Project A | Design | Final Design | 11/18/2019 | 6/15/2020 | 210 |
514 | Project A | Design | Environmental | 10/28/2019 | 10/7/2020 | 345 |
515 | Project A | Design | Final Design | 12/26/2019 | 9/29/2020 | 278 |
516 | Project A | Design | Final Design | 5/29/2020 | 9/16/2020 | 110 |
517 | Project A | Design | Final Design | 9/17/2020 | 1/8/2021 | 113 |
518 | Project A | Design | Procurement | 1/8/2021 | 5/6/2021 | 118 |
519 | Project A | Construction | Construction | 5/6/2021 | 5/4/2023 | 728 |
Solved! Go to Solution.
there is a difference between a table, and a table visual. The former has your data, the latter is a Power BI User interface element.
On the right is a table. On the left are visuals, and the highlighted one is a table visual.
There are many ways that can be done. One would be via SUMMARIZE(), another one via ALLEXCEPT() etc. What have you tried so far?
I've tried the calculate (https://community.powerbi.com/t5/Desktop/getting-the-max-and-min-date-of-a-group/td-p/680844); i've tried the allexcept (https://community.powerbi.com/t5/Desktop/Help-With-finding-the-earliest-Date/td-p/146353); i've tried https://community.powerbi.com/t5/Desktop/Using-earliest-and-latest-dates/td-p/574672.
I've tried so many they've all blurred together! I feel like maybe I'm conflating a few different ones at this point.
Here's a very simple example. Put your Project Name in a table visual and then add this measure
Max Duration = CALCULATE(datediff(min('Duration'[Actual Start]),max('Duration'[Actual/Forecasted Finish]),DAY))
(I added a Project B with a different end date to show the difference)
Your output is exactly what I want! When I used your code with my table name, I get "The expression specified in the query is not a valid table expression."
Can you explain what you mean by putting my project name into a table visual?
Thank you so much for your help!
"When I used your code with my table name, I get "The expression specified in the query is not a valid table expression.""
Please elaborate. I don't understand what you are doing.
In your pbix file go to the UI section, place a table visual onto the canvas, add the "Project Name" column to the visual.
Am I understanding you to say that I have to have two tables? My original table that I pasted a section of in my original post, and another table of project names?
there is a difference between a table, and a table visual. The former has your data, the latter is a Power BI User interface element.
On the right is a table. On the left are visuals, and the highlighted one is a table visual.
I have never been so thankful for smart computer people in my LIFE!! You are amazing and moved to the top of the "gold star for being awesome" list.
My disconnect was thinking it was a column, not a measure. This works perfectly!
User | Count |
---|---|
13 | |
8 | |
8 | |
7 | |
5 |
User | Count |
---|---|
21 | |
15 | |
15 | |
10 | |
7 |