Each project has stages, and each stage has tasks. Each task has a task completion %.
I'm currently using a normal Average Formula - 

Stage/Task/Phase Completed % = AVERAGE('FACTS_Projects/Stage/Task'[Task Complete %])
and I get the values below (this is the task level)

Nindo_0-1631168793487.png

 

 

so, when I look at the value at the stage level, I expect to get for each stage (60+20) / 2 tasks = 40%

But instead I get 5%

Nindo_1-1631168582798.png

What am I doing wrong?

1 ACCEPTED SOLUTION
Tanushree_Kapse
Impactful Individual
Impactful Individual

Hi @Nindo ,

Use the below measure:

Stage/Task/Phase Completed % =
CALCULATE (
    AVERAGE ( Table[Task Complete %] ),
    FILTER ( ALLSELECTED ( Table ), Table[stage name] = MAX ( Table[stage name] ) )
)

 

 

Mark this as a solution, if I answered your question. Kudos are always appreciated.

Thanks

View solution in original post

1 REPLY 1
Tanushree_Kapse
Impactful Individual
Impactful Individual

Hi @Nindo ,

Use the below measure:

Stage/Task/Phase Completed % =
CALCULATE (
    AVERAGE ( Table[Task Complete %] ),
    FILTER ( ALLSELECTED ( Table ), Table[stage name] = MAX ( Table[stage name] ) )
)

 

 

Mark this as a solution, if I answered your question. Kudos are always appreciated.

Thanks

Helpful resources

Announcements
August Power BI Update Carousel

Power BI Monthly Update - August 2025

Check out the August 2025 Power BI update to learn about new features.

August 2025 community update carousel

Fabric Community Update - August 2025

Find out what's new and trending in the Fabric community.